Release Schedule

Revision:  r1

Activity Log

DateRevEvent or UpdateMilestones Affected

 

r1

The TSC approved a proposal to push M1 out by two weeks to avoid conflicting with the updated London schedule.

Also added D&TF event and updated date for London Sign Off.

M1

 

initial draftThe TSC approved the proposed schedule.ALL

 


Met with ODL to review Montreal schedule.  The draft schedule appears to be a good fit for projected ODL release activities.  The plan is to integrate the ODL Argon release. 

No updates to the Montreal draft required.

ALL

 


Initial draft postedALL