You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 53 Next »



Beijing Release

This release calendar proposal has been presented to the Community at the Developers F2F in Paris on Sept 27, and have been updated to incorporate the feedback received.

Beijing Release Planning

Link to ONAP Beijing Release Planning (PDF)

Beijng Release Calendar

Review MilestoneDateEvents
Kick-Off (Open Intent To Participate)M0November 16, 2017

Opening of Release Planning

Project Submission Closure
November 30, 2017

Last Date to announce Intention to Participate

Project Proposal Approved
December 13, 2017The TSC has a goal to review and provide its disposition on all submitted projects proposal.

This is the last date for TSC to formally approved New Project Proposal

Project Planning Closure
Jan 8, 2017

Project Planning submission, by this date all projects have submitted in wiki their Release Planning materials.

That will give everyone to time to understand project scope and dependencies.

PlanningM1Jan 18, 2018

Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...)

Integration Team has defined the vendor Equipments list and the End 2 End Release Test Cases are fully defined.

The Document and Training teams have defined their plans. The packaging and installation strategy is defined.

To pass the M1 milestones, all approved projects have to:

  1. Fill out the Release Planning Template
  2. Fill out the Deliverables for Planning Milestone Checklist Template
  3. Post these 2 project deliverables in wiki.
Functionality freezeM2Feb 15, 2018

Functionality freeze, no new visible functionality is to be added to the current ONAP release.

Each Project team has defined and documented their Functional Test Cases.

The vendor equipments have been delivered.

A stable document describing the API is documented and available in wiki.

API FreezeM3March 1, 2018

API/data model freeze. Mark the end of API and Data Model change. API and Data Model are now Frozen.

Any changes to the API must be brought to the knowledge of the TSC for review and approval.

50% of Functional Test Case are automated.

Code FreezeM4Avril 5, 2018

Code Freeze. Mark the end of the Features coding.

Jira issues are either fixed in the current release or assigned to next release.

100% of Functional Test Case are automated.

End 2 End Release Test Cases are implemented (Integration Team).

IntegrationRC0Avril 19, 2018

Release Candidate 0

RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases.

Project Team focused its effort on:

  1. supporting integration testing
  2. closing high priority defects
  3. supporting Documentation team

RC1May 3, 2018Release Candidate 1

RC2May 17, 2018Release Candidate 2
Sign-OffRelease DeliveryMay 24, 2018Beijing Release Sign-Off

Amsterdam Release

Amsterdam Release Planning 

Amsterdam Release Calendar

Link to ONAP Amsterdam Release planning (PDF).

Amsterdam Release Calendar


Review MilestoneDateEvents
Kick-Off (Open Intent To Participate)M0May 4, 2017Planning process opens for all projects to submit their intent.
Project Submitted
May 15, 2017

All projects candidate for the first ONAP Release have to:

  1. use the Project Proposal Template
  2. post the proposal in the wiki at Proposed Projects
  3. inform ONAP TSC of their intention throught the ONAP TSC mailing list.
Project Approved
June 1, 2017The TSC has a goal to review and provide its disposition on all submitted projects proposal.
PlanningM1June 29, 2017

Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...)

Integration Team has defined the vendor Equipments list and the End 2 End Release Test Cases are fully defined.

The Document and Training teams have defined their plans. The packaging and installation strategy is defined.

To pass the M1 milestones, all approved projects have to:

  1. Fill out the Release Planning Template
  2. Fill out the Deliverables for Planning Milestone Checklist Template
  3. Post these 2 project deliverables in wiki.
Functionality freezeM2August 03, 2017

Functionality freeze, no new visible functionality is to be added to the current ONAP release.

Each Project team has defined and documented their Functional Test Cases.

The vendor equipments have been delivered.

A stable document describing the API is documented and available in wiki.

API FreezeM3August 24, 2017

API/data model freeze. Mark the end of API and Data Model change. API and Data Model are now Frozen.

Any changes to the API must be brought to the knowledge of the TSC for review and approval.

50% of Functional Test Case are automated.

Code FreezeM4Sept 28, 2017

Code Freeze. Mark the end of the Features coding.

Jira issues are either fixed in the current release or assigned to next release.

100% of Functional Test Case are automated.

End 2 End Release Test Cases are implemented (Integration Team).

IntegrationRC0Oct 12, 2017

Release Candidate 0

RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases.

Project Team focused its effort on:

  1. supporting integration testing
  2. closing high priority defects
  3. supporting Documentation team

RC1Oct 26, 2017Release Candidate 1

RC2Nov 9, 2017Release Candidate 2
Sign-OffRelease DeliveryNov 16, 2017Amsterdam Release Sign-Off


Amsterdam Release Dependencies

API Dependencies

The source of information to generate this information are the data point gathered into the project Release Planning template.

The graph below represents API dependencies for M1 Release Planning projects.

More info on how to generate the graph are available.

ONAP API Dependencies

ONAP Release Lifecycle

  • Release Lifecycle. It provides a description of each of the above milestones and the activities to be implemented.
  • No labels