ONAP Release 1 Release Planning Draft Proposal

ONAP Release 1 Planning Proposal Draft

Link to ONAP Release 1 planning PPT.

Release Calendar


Review MilestoneDateEvents
Kick-Off (Open Intent To Participate)M0May 4, 2017Planning process opens for all projects to submit their intent.
Project Submitted
May 15, 2017All projects candidate for the first ONAP Release have to use the Project Proposal Template, post the proposal in the wiki at Proposing A Project and inform ONAP TSC of their intention throught the ONAP TSC mailng list.
Project Approved
June 1, 2017The TSC has a goal to review and provide its disposition for all submitted projects.
PlanningM1June 29, 2017

Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...)

Integration Team has defined the vendor Equipments list.

The Document and Training teams have defined their plans.

The packaging and installation strategy is defined.

Functionality freezeM2August 03, 2017

Functionality freeze, no new visible functionality is to be added to the current ONAP release.

Each Project team has defined functional Test Case.

The vendor equipments have been delivered.

A stable document describing the API is documented and available.

API FreezeM3August 24, 2017

API/data model freeze. Any Changes to the API must be brought to the knowledge of the TSC for review and approval.

50% of Test Case are automated.

Code FreezeM4Sept 14, 2017

Code Freeze. Mark the end of the Features coding.

Jira issues are either fixed in the current release or assigned to next release.

100% of Test Case are automated.

IntegrationRC0Sept 28, 2017Release candidate 0

RC1Oct 12, 2017Release candidate 1

RC2Oct 26, 2017Release candidate 2
Sign-OffRelease DeliveryNov 2, 2017Target release date



Release Lifecycle

  • Release Lifecycle proposal draft. It provides a description of each of the above milestones and the activities to be implemented.