    • ARCHITECTURE SUB-COMMITTEE - The following are M0 activities with the Architecture Sub-committee. Release content defined.
      • #1 FUNCTIONAL ARCHITECTURE (Proposals) - The functional reference architecture is the high-level architecture overview diagram for all of ONAP. Enhancements to the functional architecture may be driven by new project proposals, updates to the diagram, and architectural changes that may be planned for the release. At M0 impacts to the functional architecture are proposed.
      • #2 COMPONENT ARCHITECTUREARCHITECTURE (Proposals) - The component architecture impacts originate from the ONAP platform components. Examples of platform components are SO, A&AI, CCSDK, SDN-C. Each release there may be architecture impacts from the platform components. At M0, component architecture impact proposals are submitted. Architecture reviews are setup & scheduled for component architecture impacts/proposals. Component architecture diagrams would be updated.
      • #3 REQUIREMENTS ARCHITECTUREARCHITECTURE (Proposals) - These are architecture impacts coming from the requirements and use case work in a release that may impact the functional architecture, platform architecture, or may need architectural guidance. At M0, the requirements and use cases are being proposed for the release. And an early assessment of which ones that might impact the architecture should be considered, and they made translate into requirements architecture proposals. Architecture reviews are setup & scheduled for requirements architecture impacts/proposals.
      • #4 ARCHITECTURE ENHANCEMENTSENHANCEMENTS (Proposals) - Architecture enhancements are secondary architectural enhancements that are worked during a release. These may include documentation enhancements, landing page enhancements, architecture component description work, flow descriptions and process work. At M0, initial proposals are submitted to the architecture sub-committee.
    • WIKI LINKS References for the Use Case Teams at M0

      WIKI LINKS REFERENCE AT M0
      M0DescriptionWiki Link
      1Functional Reference ArchitectureArchitecture
      2Architecture Portal Page
      https://safratech.net/onapdocs/
      3Release Architecture Page

      All of the architecture reviews that were conducted:


      4Requirements Proposals

      Requirements subcommittee

      Guilin release - functional requirements proposed list

      6Release Tracking pageRelease Planning
      ModModeling Release Planning PageONAP R7 Modeling High Level Requirements


    • Modeling team - At MO the Modeling S/C does MODEL PLANNING. The planning develops into “High Level Info-model Requirements”. These High level info-model requirements fall into 3 categories:
      • #1: NEW USE CASES - items from the expected Use Cases in the release (Scope of modeling, continuing, introducing, standards updates). The Use Case Teams should engage the modeling team to propose new requirements into their release planning page.
      • #2: REFINING EXISTING MODEL - Refining Existing info-model that has not made it to the information model. Previously designs that need to be added into information model.
      • #3: FORWARD LOOKING WORK (FLW) - Modeling future forward looking requirements.
    • USE CASE TEAMS At M0, the Use Case teams are working on the following things:
      • #1: BUSINESS DRIVER TEMPLATE - The Use Case Teams are specifying their business drivers via the template: Business Driver Template for Use Cases
      • #2: REQUIREMENTS SUB-COMMITTEE - Develop their proposals for the release to the Requirements Sub-committee: Requirements subcommittee
      • #3: REQUIREMENTS RELEASE TRACKING - After making a presentation to the Requirements sub-committee, requirements are put into the release proposed functional requirements page. An example for Release 7 (GuiLin) is at this wiki: Guilin release - functional requirements proposed list
      • #4: USE CASE DEFINITIONS - Use Case team fill out the Template detailing their Use Case: Use Case Tracking Template
      • #5: INTENTION TO PARTICIPATE - Teams can indicate their corporate intention to participate
      • #6: RELEASE TRACKING - Each release has a release tracking page. The page can be found here: Release Planning
      • #7: PROJECT SUBMISSION, PROPOSAL, PLANNING - The TSC coordinates the project submission, proposal and planning. The TSC reviews and provides its disposition on all submitted projects proposal. These are also tracked on the Release Planning page.
    • PTL- High level release scope from PTLs (understand from PTL which ONAP components are expected to have updates)
    • PTL - The Use Case teams should attend the PTL planning meetings if there are expected to be requirements impacts for your use case. It is also where the Release Planning page is developed by the PTL team.

...

Devloping updates on an API. related info-modeling activity.


  • M1

    • ARCHITECTURE SUBCOMMITTEE at M1 -
      • #1 FUNCTIONAL ARCHITECTURE (Requirements) - The functional reference architecture is the high-level architecture overview diagram for all of ONAP. Enhancements to the functional architecture may be driven by new project proposals, updates to the diagram, and architectural changes that may be planned for the release. At M0 impacts to the functional architecture are proposed.
      • #2 COMPONENT ARCHITECTURE (Requirements) - The component architecture impacts originate from the ONAP platform components. Examples of platform components are SO, A&AI, CCSDK, SDN-C. Each release there may be architecture impacts from the platform components. At M0, component architecture impact proposals are submitted.
      • #3 REQUIREMENTS ARCHITECTURE (Requirements) - These are architecture impacts coming from the requirements and use case work in a release that may impact the functional architecture, platform architecture, or may need architectural guidance. At M0, the requirements and use cases are being proposed for the release. And an early assessment of which ones that might impact the architecture should be considered, and they made translate into requirements architecture proposals.
      • #4 ARCHITECTURE ENHANCEMENTS (Requirements) - Architecture enhancements are secondary architectural enhancements that are worked during a release. These may include documentation enhancements, landing page enhancements, architecture component description work, flow descriptions and process work. At M0, initial proposals are submitted to the architecture sub-committee.
    • USE CASE TEAMS - The Use Case Teams prepare their proposals. At M1 the project submission, proposal and planning have occurred with the TSC. Use Case teams are cross-functional in nature: they are composed of a leader, developers and also (indirectly) the ONAP platform members from components that need to be involved. Working towards M1, the Use case teams are defining their requirements and starting to craft a Data Model. 
      • #1 RELEASE PLANNING TEMPLATE - Use the release planning template to help you think about your scope, minimum viable product, architecture, risks, and epics. The release planning template can be found here: Release Planning Template
      • #2 MILESTONE CHECKLIST - The milestone checklist template are used by the Use Case teams. This checklist can be found at this wiki link: Deliverables for Planning Milestone Checklist Template
      • #3 PROJECT DELIVERABLES - are defined including functional architecture, scope, dependencies.
      • #4 MODELING TEAM WORK - The model subcommittee team becomes aware of the use cases for the current release.
      • #5 EARLY DATA MODEL CONCEPTS - Because the information model feeds the data models, the Use Case teams should take into account the new updates in the information model as a basis for their data model.
      USE CASE TEAMS - The Use Case Teams prepare their proposals. At M1 the project submission, proposal and planning have occurred with the TSC. Use Case teams are cross-functional in nature: they are composed of a leader, developers and also (indirectly) the ONAP platform members from components that need to be involved. Working towards M1, the Use case teams are defining their requirements and starting to craft a Data Model. 
      • #1 RELEASE PLANNING TEMPLATE - Use the release planning template to help you think about your scope, minimum viable product, architecture, risks, and epics. The release planning template can be found here: Release Planning Template
      • #2 MILESTONE CHECKLIST - The milestone checklist template contains a master blueprint of all of the major areas of a use case that need to be tracked. The Use Case teams should discuss and fill out for themselves this milestone checklist, and particularly, the product management and release management sections. The major topic areas of the checklist are: documentation, security, product management, release management, testing & integration and development. This checklist can be found at this wiki link: Deliverables for Planning Milestone Checklist Template
      • #3 PROJECT DELIVERABLES - are defined including functional architecture, scope, dependencies.
      • #4 MODELING TEAM SYNC - The model subcommittee team should become aware of the use cases for the current release. Use Case teams are expected to make presentations to the modeling sub-committee for use cases that may impact the information model. This should open a dialogue between the Use Case team and the modeling to identify model impacts and where there might conceptual overlaps to help streamline the design. The Use Case teams may also be agnostic to the broader information model and contact between the modeling sub-committee and the use case teams will also raise awareness of relevant information models that the Use Case teams will need.
      • #5 EARLY DATA MODEL CONCEPTS - Because the information model feeds the data models, the Use Case teams should take into account the new updates in the information model as a basis for their data model. The Use case teams should be identifying three things which will help the Modeling subcommittee understand better the model impacts. This will help the modeling team identify areas where model impacts will be. The Use Case teams should define their use cases in more detail ideally using the inputs, outputs and data flows.
      • PRECONDITIONS - Preconditions are the Information the use cases consume.
      • POST-CONDITIONS - The post-conditions can capture the kind of information that is output from the use cases.
      • INFORMATION EXCHANGES - information exchanges capture the type of information that passes from component to component, APIs, NBI and external interfaces. This helps to identify the relevant models that give that exchanged information structure
    • WIKI LINKS References for the Use Case Teams at M1

      WIKI LINKS REFERENCE AT M1
      M1DescriptionWiki Link
      1Release Planning TemplateRelease Planning Template
      2Milestone ChecklistDeliverables for Planning Milestone Checklist Template
      3Modeling High Level RequirementsONAP R6 Modeling High Level Requirements




    • Project & Release planning tables
    • Modeling team The info-model plan is established by the modeling team which summarizes the modeling requirements for a release. The model planning follows a template that is worked by the team. Info-model updates begin. An example template for R6 (Frankfurt) can be seen at this Wiki: ONAP R6 Modeling High Level Requirements.
      • #1: SYNC - The Use Case teams need to engage the Modeling Sub-committee to make the team aware of model impacting use cases. The modeling team should also become aware of at a high-level what impacts a use case might have. The use cases also need to get into the ONAP Modeling High-level requirements planning page.
    • Architecture - Every release, the architecture sub-committee refines the functional architecture, creates new flow updates, and may update component architectures.
      • #1: SOCIALIZATION - The Use Case teams should become aware of the new functional architecture and component architecture changes for the current release. Architecture should become aware of new modeling concepts. Cross-fertilization of new requirements, use cases and how they might impact model or how the model impact the upcoming proposed architecture changes. The idea is that the use case leads would queue some time in one of the architecture S/C calls (as a 1-off) to discuss the use cases that may impact platform components for that release. The Use case teams can reserve some time on the Architecture sub-committee team meeting to align the use cases with the architecture. The Architecture lead (PTL) can also flag impacts of the functional architecture to use cases and vice versa.
    • Components (PTL)- Each of the ONAP platform components (e.g. A&AI, SO, Controllers, SDC etc) may be impacted by new use cases. Having the use case leads engage PTLs.
      • #1: COMMITMENT & TRACKING - The data model developed by the use case teams eventually serve as the basis for API changes. Platform components need to update APIs based on new requirements, use cases and features. Requests to components need to be tracked & commitment by the PTLs and components. Ideally the PTLs and component leads should be engaged by the Use Case teams. SDC & A&AI often have more high-running modeling impacts than some of the other components. The modeling team members could attend some of the component calls to raise awareness. Identifying and tracking a modeling impacting item so they aren't lost. An issue impact matrix and tracking page could be developed to track issues (and maybe a Jira ticket).
      • #2 RELEASE TRACKING PAGE - The release tracking page also tracks the platform components.

...