vFW / vDNSBrian Freeman / Marco Platania

--@TLab and Windriver

Status:  Passed on boarding and instantiation. Passed on closed loop for vFW (with manual patch on staging env)

vCPE Integration Test Case: Yang Xu

--@Windriver

Status: If use firefox browser, (on service design); going on (blocked by the portal port, need to change back to 8989: PORTAL-436 - change port from 8989 to 30215 for OOM deployment Closed

Will retest today. (Yang will update later today at 10/31/2018)

vCPE with TOSCA VNF Integration Test Case: Yang Xu / Itohan Ukponmwan

--@Windriver (Intel)  / @CMCC (China Mobile ...)

Status:

Intel: The testing has been started at Intel, and start testing at SB-06 with HPA. Trying to setup OOM SB-06, (install staging after APPC health check be fixed)

CMCC: 

ONAP deployment have finished

Device have been  ready and begin to install openstack  Pike which used to deploy VNF

Design time testing have started  (Yang will send out an email to ask them)

5G - Real Time PM and High Volume Stream Data Collection - Integration Test CasesMarcin Przybysz Marek Pondel

--@TLab

Status: It has been passed the test at Nokia lab. All pairwise testing has done at Windriver lab. End to end testing has done with staging. Will re-test with release when it is ready.

5G - PNF PnP - Integration Test CasesMarcin Przybysz Krzysztof Kuzmicki

--@TLab

Status: End to end test case has been implemented at Nokia lab. It has been blocked by AAI-1772.

5G - Bulk PM - Test Status: user-3784d Liam Burke

--@TLab

Status: Waiting for ONAP being installed successfully.  (Needs update 10/31???)

5G - OOF and PCI - Integration Test Cases:  N.K. Shankaranarayanan

--@Rutgers Winlab ONAP Wireless Lab (OWL)

Status: Ongoing. For test cases, please see Test aspects . New software modules being installed in OWL lab . Upgraded ONAP from Beijing to Casablanca. Doing PoC for C release, mostly related to Policy, OOF.

Latest: Paring wise testing with OOF is being done. Others is waiting for the full installation with OOM in testing lab with Casablanca.

5G - PNF Software Upgrade - Integration Test Cases: Yang Xu

--@Windriver Lab

Status: It has been passed the test at Huawei lab. Re-test it at Windriver lab. (Not started yet,  not much dependency on other components)

Scale Out - Integration Test Cases and Status: Scott Blandford, Marco Platania

--@Windriver Lab

Status: Created policy, control loop, deploy control loop into dcae. (with http and https connections) (At this moment, HEAT). Testing with OOM based deployment: passed distribution and instantiation with walkaround DMAAP/CLAMP.  ( CLAMP-216 - Getting issue details... STATUS ) Still have communication between containers with CDT.

Design closed loop for scale-out: PASS

Runtime for scale VF module (a working session at 10/24 afternoon).  (Need to check with Marco for update)

CCVPN Integration Test Cases: Yang Xu

--@CMCC

Status: Demoed at ONS Europe. The optical equipment has delivered to CMCC, and they are manually testing the optical equipment.


Deploy ONAP using OOM  basically completed: DONE

Huawei sotn manual testing have completed

ZTE sotn manual testing begin (Yang will follow up with them)

HPA & Cloud Agnostic Intent - R3 Test PlanItohan Ukponmwan

--@Windriver Lab

Status: The testing has been started at Intel, and start testing at SB-06 with HPA.


Change Management - Flexible Designer & Orchestrator - Ajay Mahimkar, Elena Kuleshov, Priyanshu Agarwal, Chris Rapposelli 

Status: Testing in progress on SB-04


Change Management - Traffic Management- Lukasz Rajewski & Tomasz Osinski

Status: Testing completed by Orange (Lukasz and Tomek) in SB-07 using vFW


Change Management - 5G PNF in-place software upgrade- Yaoguang Wang & Ruchira Agarwal 

Status: Testing completed by Huawei (Yaoguang) in Huawei lab using EM and PNF emulator


Change Management - Schedule optimization - Ajay Mahimkar & Jerry Flood

Status: Modifications put in place (MariaDB) and deployment in progress. Testing will begin after deployment.