Integration Test Working session (weekday): UTC 17:00 / Eastern 13:00 / Pacific 10:00 daily @ https://zoom.us/j/4466668888 before RC2



Use CaseLabResponsibleStatusUse Case Details Testing StatusQuick Notes
1vFW / vDNS
  • Intel / Windriver

COMPLETED ON STAGING

BROKEN

vFW / vDNS

Passed on boarding and instantiation. Passed on closed loop for vFW (with manual patch on staging env) at one time, but currently is broken.

SDNC Preload - PASS

VID Preload - PASS    - See VID Preload Upload Option Steps

APPC-1237 - Getting issue details... STATUS

SO-1186 - Getting issue details... STATUS

2

vCPE Integration Test Case

Intel / Windriver

50% WIP

vCPE Integration Test Status

Onboarded 5 HEAT templates for infra, vbrg, vbng, vgmux and vgw, and created 5 VNFs.

Finished services creation and distribution

Infra, vBRG, vBNG, vGMUX have instantiated

SO-1184 - Getting issue details... STATUS

3

vCPE with TOSCA VNF Test Case

  • Intel/Windriver
  • CMCC

Yan Yang

Yang Xu (liaison)



30% WIP

vCPE with TOSCA VNF Integration Test Status

Intel: The testing has been started at Intel, and start testing at SB-06 with HPA. Trying to setup OOM SB-06, (install staging)

CMCC: 

Redeployed ONAP due to resource limitation, restarting design time testing

4

5G - Real Time PM and High Volume Stream Data Collection - Integration Test Status

TLab

90% WIP

COMPLETED ON STAGING

NEEDS RETESTS ON RELEASE

5G - Real Time PM and High Volume Stream Data Collection - Integration Test Status

It has been passed the test at Nokia lab. All pairwise testing has done at Windriver lab. End to end testing has done with staging. Will re-test with release when it is ready.

5

5G - PNF PnP - Integration Test Status

TLab

70% WIP

5G - PNF PnP - Integration Test Status

We were able to run whole flow, but we found out new issue. SO communicate with PRH using wrong topic.

Bug SO-1191 - Getting issue details... STATUS  is raised. Fix planned to be delivered 9.11 EOD

6

5G - Bulk PM - Test Status

TLab

COMPLETED

5G - Bulk PM - Test Status

It has passed the tests at Ericsson lab
7

5G - OOF and PCI - Integration Test Cases

Rutgers Winlab ONAP Wireless Lab (OWL)

WIP

5G - OOF and PCI - Integration Test Cases

 For test cases, please see Test aspects . New software modules being installed in OWL lab . Upgraded ONAP from Beijing to Casablanca. Doing PoC for C release, mostly related to Policy, OOF.

Latest: Paring wise testing with OOF is being done. Others is waiting for the full installation with OOM in testing lab with Casablanca.

8

5G - PNF Software Upgrade - Integration Test Cases

Intel / Windriver

30% WIP


It has been passed the test at Huawei lab. Re-test it at Windriver lab. (Not started yet,  not much dependency on other components)
9

Scale Out - Integration Test Cases and Status

Intel / Windriver

67% COMPLETE

Scale Out - Integration Test Cases and Status

Design time


We tested this part before successfully, however today we failed a few steps:


  • CLAMP didn’t automatically load the closed loop properties. We did manually via the GUI. Note that we had an issue with SDC back end this morning, I’m not sure that could have affected CLAMP as well. 
  • CLAMP successfully created configuration and operational policies in Policy, but the payload section was wrong. This is actually a new test, in the past we used mock data. The error is a simple format incompatibility that I guess Seb and Jorge already worked out. A new CLAMP container with fixes should be already running in SB04.
  • DCAE didn’t upload the closed loop sent by CLAMP. Initially, the issue was instability in the DCAE environment. Later on, the issue was a wrong blue print version. We didn’t retry, but should be an easy fix.

Runtime

Although the issue encountered at design time prevented to make SO calls via Policy, I made the same calls with Postman. This is the status:

  • CatalogDB in SO needs some tables to be updated. Fixed manually thanks to Steve and I was good to go. Jira ticket open to make those changes permanent:https://jira.onap.org/browse/SO-1174 Prema is looking at that.
  • Part 1 of the scale out workflow: VNF health check. The call to APPC client fails due to property error. Prema is on this as well https://jira.onap.org/browse/SO-1175 I ran this with my Postman and it succeeded. APPC was able to actually run health check against the VNF. On a side note, I used REST in APPC/CDT for health check. Seems that APPC issues only http queries against the VNF, not https (not required anyway, the VNF supports both)
  • Part 2 of the scale out workflow: VNF scale out. This went on almost till the end, when it failed due to SO using wrong SDNC preload. Ticket open and assigned to Brittany (for the moment – SO team can redistribute): https://jira.onap.org/browse/SO-1177
10CCVPN Integration Test Cases:cmcc

Yan Yang

Yang Xu (liaison)

30% WIP

CCVPN Integration Test Cases:Demoed at ONS Europe. The optical equipment has delivered to CMCC, and they are manually testing the optical equipment.


Deploy ONAP using OOM  basically completed: DONE

Huawei sotn manual testing have completed

ZTE sotn manual testing has finished

Finished resource design (resource template import) and service design

11

HPA & Cloud Agnostic Intent - R3 Test Plan:

Intel / Windriver

15% WIP


The testing has been started at Intel, and start testing at SB-06 with HPA.
12Change Management - Flexible Designer & Orchestrator Intel / Windriver

66% COMPLETED


Testing in progress on SB-04

1) SO uploading a list of activities/building blocks to SDC - successfully tested

2) Design workflow in SDC and distribute to SO is completed successfully! Thanks to Michael & Priyanshu for resolving issues.

3) Deploy workflow in SO and orchestrate the execution of the workflow - To Do

13Change Management - Traffic Management-Intel / Windriver

Lukasz Rajewski

Tomasz Osinski

COMPLETED


Testing completed by Orange (Lukasz and Tomek) in SB-07 using vFW
14Change Management - 5G PNF in-place software upgradeIntel / Windriver

COMPLETED


Testing completed by Huawei (Yaoguang) in Huawei lab using EM and PNF emulator
15Change Management - Schedule optimizationIntel / Windriver

COMPLETEDFunctional testing completed. E2E testing in Dublin.


Functional testing completed by Jerry in OOM Staging Daily Windriver.