  1. PNF presentation by Eliezio Oliveira(Ebo)
    1. Model-based, modular simulator 
    2. The simulator is composed by two modules: i) a Netopeer core Netconf server, and ii) a DB that hosts Yang models
    3. User provides configuration:
      1. Yang model that describes a Netconf end point
      2. initial configuration of the simulator (e.g. a JSON file that contains initial values of parameters defined in the Yang model)
      3. one or more Python scripts that include the operations that the PNF simulator executes when a change (i.e. API call) is made
    4. The simulator code is hosted by github (https://github.com/blue-onap/netconf-pnp-simulator.git) and runs as docker container
    5. The simulator can simulate different PNFs (modules) at the same time
    6. If one has to simulate multiple instances of the same PNF (module), the recommended way is to deploy multiple instances of the simulator docker container
    7. Current usage in ONAP:
      1. PNF subscription handler use case
      2. PNF software upgrade use case
    8. Possible approaches to hosting the code in ONAP repository
      1. Demo repository
      2. Integration repository
      3. Sub-repository within the Integration repository
  2. Lab status
    1. Integration-SB-01 (master branch) is almost a month old and not stable
    2. A new lab (master branch) will be created soon and information about VM access will be socialized via onap-discuss mailing list


 

  1. Feedback from the Syncho with Seccom
    1. priorities
    2. port scanning tests
      1. White list
      2. consequence on integration related pod
    3. root_pods
      1. consequence on integration related pod
      2. java docker? any jenkins expert to move that to official ONAP repo...
    4. introduction of kube-hunter (vulnerability checkers)
  2. Admin
    1. Specific Integration milestones to be defined and reported to David McBride: Integration M4 milestone possible evolution
    2. Update on Integration verification job
      1. python verification job added in Integration repo (for vCPE)
    3. alias team.onap.eu created
    4. reinsourcing of oom/robot in robot: https://gerrit.onap.org/r/c/oom/+/101605
  3. Lab Status
  4. Frankfurt status
    1. Use case update
      1. roundtable from use case owner
      2. Portal Selenium tests
        1. Is there any test plan already available in Portal
        2. If so is there any associated tests, shall we cretae on, leverage on healthportall?
      3. DCAE application deployment
      4. pnf_registrate status
      5. anyone working on and End to End "basic" CDS
    2. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
      1. Review Blocking JIRA review: 1: Frankfurt Release Integration Test Blocking Issues
      2. New A&AI regression detected (no more tenant id leading to failure of the end to end VNF tests)
    3. CI status
      1. Master status
      2. Parallelization of the VNF and security tests (to save CI time) in progress
      3. windriver CI still pending - runner is working well but clean/server creation seems to request parameters that do not fit well together
  5. AoB

(17:17:39) collabot`: Meeting ended Wed Feb 12 16:17:45 2020 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(17:17:39) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-12-14.00.html
(17:17:39) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-12-14.00.txt
(17:17:39) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-12-14.00.log.html


 

  1. Action points follow-up from last week (summarized already here to save time)
    1. #info AP1: morgan asks for LF FQDN + certificates
      #info discussion done, for the certificates => use let's encrypt and for the FQDN LF relunctant from a legal perspective to referent a web site it does not manage, possible workaround to use another domain
      #info AP2: bartek add tox for vCPE and vagrant files
      #info done WIP
      #info AP3: morgan_orange add verification-python in ci-management for integration
      #info done WIP: https://gerrit.onap.org/r/c/ci-management/+/100985
      #info AP4: organize ad hoc meeting with lab owners to share tooling and best practices
      #info not done yet
      #action morgan_orange organize ad hoc meeting with lab owners to share tooling and best practices
      #info AP5: morgan_orange contact Kzrysztof for several updates (dcae discussion/pnf_registrate/..)
      #info done topic planned this week
  2. Syncho with Seccom / OOM - 30'=> connexion on OOM zoom: https://zoom.us/j/118908904
    1. Review of the current security tests
    2. Set priority on these tests for Frankfurt
    3. Elaborate speech for PTL meeting (what do we expect from them - who is doing what)
  3. Admin => back to our zoom https://zoom.us/j/660849669
    1. Specific Integration milestones to be defined and reported to David McBride: Integration M4 milestone possible evolution
    2. Update on Integration verification job (https://gerrit.onap.org/r/c/ci-management/+/100985)
  4. Lab Status
  5. Frankfurt status:
    1. CI status
    2. Use case update
      1. Portal Selenium tests
      2. DCAE application deployment
    3. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
  6. AoB

(16:17:51) collabot`: Meeting ended Wed Feb 5 15:17:58 2020 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:17:51) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-05-14.31.html
(16:17:51) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-05-14.31.txt
(16:17:51) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-02-05-14.31.log.html


 

  1. Action points follow-up from last week
  2. Admin
    1. We are green for M2/M3 (but we should not..just found old pending gerrit (> 36h) on testsuite...
    2. Integration verification jenkins jobs: what's next?
    3. rocketchat still OK? move to slack? IRC, still time to answer to the survey: https://framadate.org/GqWLxFrflGPEZDDR
    4. Request from Release management to adjust Milestone criteria to Integration: Frankfurt Deliverables by Milestone
    5. Mentorship 2020 program launched (https://wiki.lfnetworking.org/display/LN/Project+Proposal)
  3. Lab Status
    1. round table
    2. Open discussion on monitoring tools used in the different labs
  4. Frankfurt status:
    1. CI status
    2. Use case update
      1. New security tests / sync meeting planned Seccom / OOM / Integration
      2. review use case page (based on use case leader feedback)
      3. Portal Selenium tests
      4. DCAE application deployment
    3. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
  5. AoB

(16:01:08) collabot`: Meeting ended Wed Jan 29 15:01:12 2020 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:01:08) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-29-13.59.html
(16:01:08) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-29-13.59.txt
(16:01:08) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-29-13.59.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. Windriver
        1. back in business
        2. CI Dialy chain to be build
    2. DDF
      1. Feedback on the presentations done during DDF
    3. Admin
      1. oparent update
      2. Integration jenkins jobs
        1. Integration of verification jobs on integration repository - feedback from the mail sent end of last week.
      3. rocketchat still OK? move to slack? https://app.slack.com/client/TLEFM5VD2/CL8KEE28Z
  1. Frankfurt status:
    1. CI status
    2. Use case update
      1. Discussion on 3rd party Controller mock (BBS use case)
      2. review use case page
    3. Requests from Seccom
      1. onap-java docker
      2. kubernetes CIS verification
      3. introduction of the security docker in CI chains
    4. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
  2. AoB

Minutes:

(16:02:25) collabot`: Meeting ended Wed Jan 22 15:02:29 2020 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:02:25) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-22-14.01.html
(16:02:25) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-22-14.01.txt
(16:02:25) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-22-14.01.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. Windriver Move in progress / wait for end of the week / option to deploy dev ONAP on Azure if issues
    2. DDF
      1. Who will be there?
      2. Several discussions planned (test strategy evolution, robustness/resiliency/load, gating retrospective, python sdk,...)

PDF PDF PDF 

  1. Misc
    1. still some issues to update INFO for csit repos (ticket open)
    2. still no onap-java repositories (request end of novemeber) => work done on gitlab.com see later
  1. El Alto status
    1. regression seen on Orange El Alto chain (https://orange-opensource.gitlab.io/lfn/tools/results_ts_view/) => same on other lab?
      1. error on APPC, VID, VFC..
      2. aai-aai-graphgraph still started (master change not backported to El Alto)
  2. Frankfurt status:
    1. CI status
      1. We moved away from the rolling release, in gating there are lots of pods in errors (no JIRA created yet) - at least on Azure on Orange
      2. 3 step OOM aaproachs to be reexplained in PTL meeting
    2. Integration jenkins jobs
      1. no verification jobs in integration? shall we put some? add pylint + unit tests for python based code (possible issues due to the heterogeneity of the repository
    3. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
    4. Status on use cases
      1. vcpe_tosca (@liping Yan Yang)  Video_2020-01-08_case.wmv
      2. pnf_registrate (Marcin PrzybyszKrzysztof Kuzmicki )
      3. vFW CDT (Lukasz Rajewski Marco Platania)
      4. vCPE (Bartek Grzybowski )
      5. 5G-SON (Reshmasree c )
      6. ...
    5. onap-java docker image: https://gitlab.com/onap-integration/docker/onap-java/
  3. AoB

(16:02:20) collabot`: Meeting ended Wed Jan 8 15:02:23 2020 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:02:20) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-08-13.58.html
(16:02:20) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-08-13.58.txt
(16:02:20) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2020/onap-int.2020-01-08-13.58.log.html

No meeting, Happy New year

No meeting, Merry Xmass

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. Info on Windriver Move:

        "I am writing to confirm the planned Intel/Windriver Integration Lab Move & Closure will still start from Jan 6th, 2020 as we previously communicated. Stephen and Intel team will all be onsite to facilitate this project, properly back up, shut down, de-rack/re-rack, and restore the lab. We are targeting EOD Friday, Jan. 10th, to have the lab back to service and will communicate to the community NEW VPN IP for accessing the lab.

  3. Frankfurt status:
    1. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
    2. Status on vCPE use case (Bartek Grzybowski )
    3. Status on Pawel activity on minial ONAP/Vagrant
    4. Portal Selenium test status
    5. Review of Frankfurt use cases 2: Frankfurt Release Integration Testing Status
  4. AoB

Minutes:

minutes 18122019.txt (LF IRC bot not working)

 


  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. DT labs added to onap-integration page
  3. Introduction of OTP test framework (20')
  4. El Alto status
    1. graphgraph still pending
  5. Frankfurt status:
    1. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
    2. Discussions on Portal/Selenium tests
      1. patchset to reenable portal suite: https://gerrit.onap.org/r/#/c/testsuite/+/99443/
      2. use case for such suite suggested by Andreas
        1. Policy -> SSO error
        2. SO-Monitoring -> cannot connect
        3. MSB -> Page not found (after msb.api.simpledemo.onap.org added to /etc/hosts)
        4. AAI UI -> empty page (after aai.ui.simpledemo.onap.org added to /etc/hosts)
        5. VID -> SSO error
        6. xDemo App -> Error (TLS)
      3. PORTAL-653 - Can't access AAI UI from Portal Closed
    3. New CI chains merged  + Dockerfile moved from gitlab to official ONAP repo
  6. AoB

(16:13:30) collabot`: Meeting ended Wed Dec 11 15:13:36 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:13:30) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-11-13.58.html
(16:13:30) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-11-13.58.txt
(16:13:30) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-11-13.58.log.html


 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. windriver
        1. Status of the labs: SB00 usable?
        2. gitlab-runner status
      2. E///
      3. Orange
        1. Openlab reinstalled in El Alto
      4. shall we create a dashboard showing the status of El Alto/Master for all the referenced lab (today 1 dashboard / lab)?
    2. Topics for Prague:
      1. https://etherpad.opnfv.org/p/onap_integration_prague
      2. https://wiki.lfnetworking.org/display/LN/Call+for+ONAP+DDF+Topics+-+Prague+2020
    3. Request for new repositories to manage images still pending
    4. Notification for committer promotion sent to coordinator/TSC
    5. CSIT cleaning planned for the end of the week
  3. El Alto status
    1. graphgraph still pending
  4. Frankfurt status:
    1. image java11: wait for the repositories or create them in gitlab.com..
    2. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
    3. Status daily Master
      1. JIRA open on aai data router: AAI-2727 - aai-data-router not starting after a fresh installation Open
    4. Discussion on https://docs.pact.io/ for pair wise testing
    5. CI chain evolution update status
      1. postinstall added in prototyped Daily CI chains
      2. feedback on last attempts to integrate some robot use cases
        1. pnf_registrate needs init => which onboard 8 models (~ 40') without link with the use case...
        2. sdc_sdnc_d will not be maintained on Frankfurt
        3. override / robot cm => an error can lead to a change in the default table and can trigger a crash of the system (test lead to a Keystone ref in multicloud with v3/v3)
  5. AoB

Upcoming meeting agenda: [integration] ONAP 2, Wed UTC 14:00

(16:12:45) collabot`: Meeting ended Wed Dec 4 15:12:51 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:12:45) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-04-14.59.html
(16:12:45) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-04-14.59.txt
(16:12:45) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-12-04-14.59.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. windriver
        1. Status of the labs: SB00 usable?
        2. gitlab-runner status
      2. E///
      3. Orange
    2. Topics for Prague: https://etherpad.opnfv.org/p/onap_integration_prague
  3. El Alto status
    1. graphgraph still pending
    2. 1: El Alto Release Integration Test Blocking Issues
    3. Integration & Test open JIRA for El Alto:


      TCléRésuméAttributionRapporteurPrEtatRésolutionCréationMise à jourEchéance
      Bug
      INT-1256 vcpe.py needs to remove whitepace from network_name Michal PtacekBrian Freeman
      Medium
      Open Unresolvedsept. 13, 2019nov. 13, 2019
      Bug
      INT-1182 Setup ONAP with required VNFM for OVP TOSCA VNF LCM testing Guanzhi YangKanagaraj Manickam
      Medium
      Open Unresolvedaoût 01, 2019nov. 13, 2019


      2 demandes Actualiser


  4. Frankfurt status:
    1. JIRA: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=207&quickFilter=630
    2. Status daily Master
      1. MSB end point issue fixed (healthcheck full re-increasing)
      2. Dialy chains and Gating pretty stable
    3. News from OOM
      1. work on DB consolidation in progress in OOM. Projects are migrating from their DB => official DB chart => common DB chart (shoudl save resources)
      2. interesting presentation on service mesh by OOM team (OOM Meeting Notes - 2019-11-13) => PoC planned for Frankfurt, and part of the release for the release after
    4. xtesting status PDF
  5. AoB

(16:17:38) collabot`: Meeting ended Wed Nov 27 15:17:42 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:17:38) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-27-13.59.html
(16:17:38) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-27-13.59.txt
(16:17:38) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-27-13.59.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Lab status
      1. windriver
        1. Warning: Resources not usable since Tuesday 19th ( INT-1371 - Windriver lab not responding Open )- not aware of any planned operations
        2. Lab will not be available beginning of January (move) => Impacts, workarounds
      2. E///
      3. Orange
    2. Committer promotion
    3. El Alto retrospective: El-Alto Retrospective
    4. Misc
      1. ran simulator integration repository is available: https://git.onap.org/integration/simulators/ran-simulator/tree/
      2. CSIT mail notification completed
      3. CSIT cleaning planned beginning of December
      4. docker local build script added in integration ( INT-1369 - Improve robot image building In Progress )
  3. El Alto status
  4. Frankfurt status:
    1. Status daily Master
    2. Python3 migration
      1. some robot libraries are only dealing with python 2.7: are they still used?
      2. /share/config/integration_preload_parameters.py still used?
    3. Robot pods and the WIP on moving storage access to RWO ( INT-1230 - No Need for "ReadWriteMany" access on storage when deploying on Kubernetes Reopened , OOM Deployment on Public Cloud)
  5. Round Table

(16:10:24) collabot: Meeting ended Wed Nov 20 15:10:29 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:10:24) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-20-14.05.html
(16:10:24) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-20-14.05.txt
(16:10:24) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-20-14.05.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. JIRA cleaning (Lots of JIRAs closed, Yang's Jira reassigned, ..)
    2. Committer promotion
    3. CSIT follow-up: https://jenkins.onap.org/view/CSIT/
      1. cleaning beginning of December
      2. mail notification under test (Policy)
    4. El Alto retrospective: El-Alto Retrospective
    5. Lab status
      1. windriver
        1. installation gitlab runners in progress
      2. E///
      3. Orange
        1. openlab migration to el alto planned this week
      4. OWL planned for 5G SON use case
    6. Priority topics for Prague
  3. El Alto status
    1. Status daily el alto
    2. Issues
  4. Frankfurt:
    1. Status daily Master
    2. Focus vCPE use case
    3. Status on gating / Xtesting
  5. Round Table

(16:09:02) collabot: Meeting ended Wed Nov 13 15:09:05 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:09:02) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-13-14.00.html
(16:09:02) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-13-14.00.txt
(16:09:02) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-13-14.00.log.html

 

  1. Action points follow-up from previous meeting
  2. Admin
    1. Frankfurt Admin JIRA managed: Frankfurt Milestone Status
    2. committer cleaning done, maybe time to start promoting committers now
    3. request to get new repo pending
    4. oparent update: still action needed?
    5. discussion on repositories to host use case code
      1. a repo for all (current approach with demo repo)
      2. a repo per use case demo/usecase/XX
  3. El Alto status
    1. Issues
      1. SO: OOM-2163 - SO not passing healthcheck after latest ElAlto bunch of SO to 1.5.3 Open
      2. NBI: EXTAPI-341 - NBI to SDC: API is HTTPS with port 8443 Open
  4. Frankfurt:
    1. Monitoring and resource optimization with kube-eagle (Sylvain Desbureaux 10')
    2. category review: Integration categories & testsuites discussions
    3. CSIT follow-up: https://jenkins.onap.org/view/CSIT/
    4. new use case for Frankfurt
      1. 5G SON
      2. ??
      3. are all the El Alto reference use case automatically included for Frankfurt?
    5. use case automation priorization?
      1. candidate tags from robot tests
    6. python3 migration, what is missing
  5. Lab status
    1. DT added in the list of pod (can push test results from their lab)
  6. Round Table

(15:05:22) collabot a changé le sujet en : (Meeting topic: Integration Testing Friday, 10/13/2017)
(15:05:22) collabot: Meeting ended Wed Nov 6 14:05:28 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(15:05:22) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-06-13.01.html
(15:05:22) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-06-13.01.txt
(15:05:22) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-11-06-13.01.log.html

 

  1. Action points follow-up from previous meeting
  2. El Alto status
    1. Testing Status: 2: El Alto Release Integration Testing Status
    2. Blockers Review: 1: El Alto Release Integration Test Blocking Issues
    3. CSIT follow-up: https://jenkins.onap.org/view/CSIT/
  3. Admin
    1. committer cleaning process
    2. archiving 2 repositories integration/benchmarking and integration/devtools
    3. update of the frankfurt pages
  4. Frankfurt: review page ONAP "Use Case/Requirement" Integration Lead
  5. Frankfurt: Proposal on Integration Gating (Morgan 20') frankfurt_integration_gate.pdf
  6. Round Table

(15:26:06) collabot: Meeting ended Wed Oct 30 14:26:12 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(15:26:06) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-30-12.58.html
(15:26:06) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-30-12.58.txt
(15:26:06) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-30-12.58.log.html

 

  1. Action points reviewed
  2. Documentation
    1. Read the docs not getting updated on patch submissions/merges to elalto
      1. Brian to follow up with Eric
    2. Please update integration page with documentation review status 2: El Alto Release Integration Testing Status
  3. El Alto Stability Run Notes
  4. Testing status - last item to be resolved with manual work arounds and completed in Frankfurt
  5. Blockers
    1. Brian to follow up on Multicloud issue with Andrew to see if documentation update is the repair
    2. SDNC 1.7.5 container to be applied manually in oom charts if user is testing this flow
  6. Lab status
    1. nothing new
  7. CSIT
    1. DCAE failures 9 and 10 days old - Marco to reach out to Vijay
      1. DCAE 3 failing due to dfc problem - a good catch by CSIT tests
    2. APPC - brian to send note to taka
    3. SDC - Discussions going on but no results to understand the root cause
  8. Testing categories deferred till next week
  9. release daily job is doing master git clone integration - ignoring command line option for elalto
  10. Round Table


 

  1. Action points follow-up from previous meeting: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.html
  2. Admin
    1. PTL Election
    2. El Alto
      1. branch, tags
      2. release note
  3. El Alto last miles
    1. Testing Status: 2: El Alto Release Integration Testing Status
    2. Blockers Review: 1: El Alto Release Integration Test Blocking Issues
    3. lab status (windriver / E///,  Orange)
    4. 72h duration test
    5. documentation update
  4. Performance Testing
    1. Longevitiy Lab?
    2. What kind of tests
  5. Frankfurt Epic prioritization
  6. Round Table

(16:04:49) collabot: Meeting ended Wed Oct 16 14:04:55 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:04:49) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-16-12.59.html
(16:04:49) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-16-12.59.txt
(16:04:49) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-16-12.59.log.


2019-10-09 Integration Weekly Meeting

  1. Action points follow-up from previous meeting: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.html
  2. El Alto last miles
    1. Testing Status: 2: El Alto Release Integration Testing Status
    2. Blockers Review: 1: El Alto Release Integration Test Blocking Issues
    3. lab status
    4. 72h duration test
    5. documentation update
  3. Admin
    1. El Alto branching
    2. PTL election
  4. Frankfurt Epic review discussions
  5. Performance Testing
    1. Longevitiy Lab?
    2. What kind of tests
  6. Round Table

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-09-13.03.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-09-13.03.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-09-13.03.log.html


2019-10-02 Integration Weekly Meeting

  1. Action points follow-up from previous meeting
  2. News
    1. New end date;  moved out to 10/3 with release signoff 10/10
    2. longevity lab wipe and deploy weekend of 9/29 - 9/29
    3. SB00 has been refreshed - main target right now until SB04 is sane again
    4. SB04 is available and should be kept current manually (Brian action to fix/repair)
    5. integration-release-daily daily install (can freeze if needed on demand)
  3. Review Testing Status
    1. Testing Status: 2: El Alto Release Integration Testing Status
      1. OOF re-install
    2. Blockers Review: 1: El Alto Release Integration Test Blocking Issues
    3. lab status
      1. E/// daily master: https://jenkins.nordix.org/job/onap-hc-full-ubuntu1804-kubespray-cloud-daily-master/16/console
      2. windriver infra tests
  4. Frankfurt Epic review
  5. Performance Testing
    1. Longevitiy Lab
  6. Round Table

(15:58:01) collabot`: Meeting ended Wed Oct 2 13:58:02 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(15:58:01) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.html
(15:58:01) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.txt
(15:58:01) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-10-02-13.00.log.html


2019-09-25 Integration Weekly Meeting

  1. Action points follow-up from previous meeting
  2. News
    1. New end date;  moved out to 10/3 with release signoff 10/10
    2. longevity lab wipe and deploy weekend of 9/29 - 9/29
    3. SB00 has been refreshed - main target right now until SB04 is sane again
    4. SB04 is available and should be kept current manually (Brian action to fix/repair)
    5. integration-release-daily daily install (can freeze if needed on demand)
  3. Review Testing Status
    1. Testing Status: 2: El Alto Release Integration Testing Status
      1. OOF re-install
    2. Blockers Review: 1: El Alto Release Integration Test Blocking Issues
  4. Performance Testing
    1. Longevitiy Lab
  5. Round Table


2019-09-18 Integration Weekly Meeting

  1. Action points follow-up
    1. CI with KaaS via LF ?
    2. CSIT changes (grooming)
    3. Multi-Arch status ?
  2. News
    1. Labs for testing
      1. SB04 - latest + patch to SDC and VID for HTTPS
        1. DCAE not coming up cleanly - DCAE team investigating DCAEGEN2-1780 - DCAE not deploying in SB04 Open
        2. instantiateVFWCL succeeds up to point of updating consul
        3. onboarding of vCPE passes up to vCPEResCust (problem in aai-ml still needs to be investigate)
        4. SDNC is 1.7.0 not latest
      2. Release Daily - will un-freeze after SDNC 1.7.2 availalbe
      3. SB00 - need to refresh after clearing DCAE issue in SB04
    2. Orange
    3. E///
  3. Review Testing Status
    1. Weather Board
    2. Pair wise testing
    3. Blockers Review
  4. Performance Testing
    1. Longevitiy Lab - wipe dublin and install El Alto - target for this weekend but at risk
  5. Round Table

(16:06:23) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-18-13.00.html
(16:06:23) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-18-13.00.txt
(16:06:23) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-18-13.00.log.html


2019-09-11 Integration Weekly Meeting

  1. Action points follow-up
    1. CI with KaaS via LF ?
    2. CSIT changes (grooming)
    3. Multi-Arch status ?
  2. News
    1. El Alto
      1. Health checks
        1. Dan sent a note - moving last applications off HTTP to HTTPS for health checks (if possible)
        2. Status on Orange daily master: 249 pods up, all chart Deployed; 3 healthcheck fail (APPC, OOF-CSMO, Portal) => JIRA already exists? if not to be created.
      2. Closed ticket on up-rev of helm/kubernetes/docker/rke
        1. INT-1231 - Bump K8S, Helm, RKE version up Closed
      3. First gating on SO (including a full chain for SO docker build) sharing the pool of CI labs with OOM
      4. doc
    2. Frankfurt Features to note
      1. DCAE VES collector https/basic auth
        1. vpp measurement reporter (vfw, vlb,vgmux ?, pnf simulator)
      2. integrate more use cases in gating (fully automated use cases)
      3. action plan for CSIT
    3. ONAP F2F September ?
  3. El Alto Early  status
    1. more release versions expected this week
    2. some containers from projects either no change or ED version
    3. use cases
    4. integration page update Q&A ? outline the process for doing the update, release, up-rev
  4. Testing Status
    1. Weather Board
    2. Pair wise testing
    3. Blockers Review
    4. oom:master - clamp is example where release in values.yaml is not available in nexus3 (open jira's on these conditions)
  5. Discussions on staging-daily/release-daily
  6. Performance Testing
    1. Feedback on the first Tests performed on Windriver infra
  7. Round Table

Minutes
(16:04:03) collabot`: Meeting ended Wed Sep 11 14:04:09 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:04:03) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-11-13.01.html
(16:04:03) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-11-13.01.txt
(16:04:03) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-11-13.01.log.html


2019-09-04 Integration Weekly Meeting

  1. Action points follow-up
    1. Stability of RocketChat and
    2. onapci.org - this is a proxy to 10.2.x.x into windriver from Azure - contact Brian if your block  (google whats my ip address and send /16 to brian)
    3. can always go direct via windriver openvpn to onapci/jenkins (Infrastrucutre tenant)
  2. El Alto Early Drop status
    1. use cases
    2. oparent
    3. integration page update Q&A ? outline the process for doing the update, release, up-rev
  3. Testing Status
    1. Weather Board
    2. Pair wise testing
    3. Blockers Review
    4. oom:master - clamp is example where release in values.yaml is not available in nexus3 (open jira's on these conditions)
  4. Action plan for CSIT tests for El Alto and beyond
    1. Morgan to propose items for PTL call on monday.
    2. Turn off jobs that are waste of time
    3. Plan for Frankfurt
    4. reward teams that are doing the right thing
  5. Discussions on staging-daily
  6. Performance Testing
  7. Round Table
    1. E/// starting daily installs on Master (version of openstack ? - kubespray)  - windriver Pike , orange Rocky , 
    2. LF has a contract with VEX Host for KaaS through jenkins job - SO verify job candidate
      1. change SO verify job to build a docker an stuff into a differnt in nexus3 ?
    3. Christina  - multi-arch effort ; planning to merge for policy this week  ; estimate some time next week ;

Minutes

(16:06:32) collabot`: Meeting ended Wed Sep 4 14:06:38 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:06:32) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-04-12.57.html
(16:06:32) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-04-12.57.txt
(16:06:32) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-09-04-12.57.log.html

2019-08-28 Integration Weekly Meeting

  1. Action points follow-up
  2. El Alto Early Drop status
  3. Focus on CSIT tests status (Lasse)
  4. Discussions on staging-daily
  5. Performance Testing
  6. Round Table

Minutes

(16:06:48) collabot`: Meeting ended Wed Aug 28 14:06:51 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:06:48) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-08-28-12.59.html
(16:06:48) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-08-28-12.59.txt
(16:06:48) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-08-28-12.59.log.html


2019-08-21 Integration Weekly Meeting

  1. Review El Alto Recent Fixes and Manual work arounds
  2. El Alto Early Drop Recommendation to TSC
  3. Environment Review (integration-design, integration-closedloop,  integration-staging-daily, integration-release-daily, SB00, SB04, dublin-longevity, dublin-closedloop)
  4. Demo Infra testing (Orangelab)
  5. Discussion of El Alto
  6. Performance Testing
  7. Other News:
    1. Windriver Distributed Open Lab ?
    2. 3rd Party Cloud tenants ?
  8. Round Table
    1. Rose  - should be done with most refactoring for El Alto - 1.5.1 is latest
    2. Itohan - environment
    3. Lasse -
      1. sdc-dcae-d - more updates for hardened components
      2. portal csit - because of hardening they stopped csit - should be re-using integration
      3. grooming existing jobs to continue PTL discussion - remove that are no longer relevant - review list - work with Dan
    4. Marcin
    5. Michael  - vcpe - vBNG/vBRG issues - brian to install in integration-release-daily
    6. Ruoyu -
    7. Morgan - infra wind river - gating changes back in - robot in synch now
    8. Marco - vFW need to wait for APPC for closedloop ; scale out dependent on CDS (Alexis/Yuri );  VID potential issue ? JIRA's ?

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-08-21-13.01.html

2019-08-14 Integration Weekly Meeting


  1. El Alto Early Drop Testing Assignments
  2. Environment Review (integration-design, integration-closedloop,  integration-staging-daily, integration-release-daily, SB00, SB04, dublin-longevity, dublin-closedloop)
  3. Discussion of El Alto Early Drop Schedule
  4. Performance Testing
  5. Other News:
    1. moved to random generated/user supplied passwords in F or G release ?
    2. https://jira.onap.org/projects/OOM/issues/OOM-1933
  6. Round Table
    1. Andrew
    2. Morgan - Orange lab is available for testing - see Orange wiki page (Orange OpenLab  )  - Orange also has Dublin on openlab and daily install of Dublin  10 PM Paris Timezone
    3. Yuriy - Post in rocket chat when SB00 is on latest AAI and healthdist works
    4. Itohan - HPA testing in OOF tenant for El Alto
    5. Lasse -  Finalizing the verification of SDC/DCAE integration tests - we can update jjb test script , TEST Jira assign to brian; CSIT tests at PTL meeting - 2 weeks with a couple PTLs
    6. Marcin
    7. Marco - heatbridge in SO - can we activate it for El Alto Release (not ED) ?
    8. MArek
    9. MAriusz
    10. Mateuse - Cassandra garbage collection issues - need a Jira kubectl -n onap top nodes ; cassandra is very very sensitive to disk performance and it can snowball
    11. Michael
    12. Daniel

IRC minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-08-14-13.06.html




2019-08-07 Integration Weekly Meeting


  1. El Alto Early Drop Testing Assignments
  2. Environment Review (integration-design, integration-closedloop,  integration-staging-daily, integration-release-daily, SB00, SB04, dublin-longevity, dublin-closedloop)
    1. longer than a day → SB00 redeploy to staging after SO 1.5.0 is available
  3. Discussion of El Alto Early Drop Schedule
    1. Recommend delaying ED by a week since we dont have release dockers from : SO, SDNC,
  4. Performance Testing
  5. Round Table
  6.  Robot
    1. Logs in AAI library - merge to testsuite causes a new staging to be built that would pick up a pythonRobotRobot
    2. manual oom chart clone till we figure out  the recurse-submodules problem (check for robot_properties.py in your clone - that means success)
  7. Up-rev to rke, k8, helm
  8. testsuite/oom repo
  9. vcpe with offline install

2019-07-24 Integration Weekly Meeting

Meeting ended Wed Jul 24 13:57:04 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-24-13.03.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-24-13.03.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-24-13.03.log.html

2019-07-17 Integration Weekly Meeting

Meeting ended Wed Jul 17 14:12:12 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-17-13.03.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-17-13.03.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-17-13.03.log.html

2019-07-10 Integration Weekly Meeting

(16:05:36) collabot` a changé le sujet en : (Meeting topic: Integration Testing Friday, 07/10/2017)
(16:05:36) collabot`: Meeting ended Wed Jul 10 14:05:39 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:05:36) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-10-13.06.html
(16:05:36) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-10-13.06.txt
(16:05:36) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-07-10-13.06.log.html

2019-06-26 Integration Weekly Meeting

Meeting ended Wed Jun 26 14:04:15 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-26-13.03.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-26-13.03.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-26-13.03.log.html

2019-06-19 Integration Weekly Meeting

(16:07:41) collabot` a changé le sujet en : (Meeting topic: Integration Testing Friday, 10/13/2017)
(16:07:41) collabot`: Meeting ended Wed Jun 19 14:07:43 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:07:41) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-19-13.00.html
(16:07:41) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-19-13.00.txt
(16:07:41) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-19-13.00.log.html

2019-06-05 Integration Weekly Meeting

(16:43:47) collabot`: Meeting ended Wed Jun 5 14:43:49 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:43:47) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-05-13.02.html
(16:43:47) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-05-13.02.txt
(16:43:47) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-06-05-13.02.log.html

2019-05-29 Integration Weekly Meeting

(16:09:45) collabot: Meeting ended Wed May 29 14:09:45 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:09:45) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-29-13.00.html
(16:09:45) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-29-13.00.txt
(16:09:45) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-29-13.00.log.html

2019-05-22 Integration Weekly Meeting

[07:03] == collabot changed the topic of #onap-int to:  (Meeting topic: Integration Testing Friday, 10/13/2017)
[07:03] <@collabot> Meeting ended Wed May 22 14:03:53 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[07:03] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-22-13.01.html
[07:03] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-22-13.01.txt
[07:03] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-22-13.01.log.html

2019-05-15 Integration Weekly Meeting

[07:09] <@collabot> Meeting ended Wed May 15 14:09:11 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[07:09] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-15-13.02.html
[07:09] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-15-13.02.txt
[07:09] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-15-13.02.log.html

2019-05-08 Integration Weekly Meeting

[07:20] == collabot changed the topic of #onap-int to:  (Meeting topic: Integration Testing Friday, 10/13/2017)
[07:20] <@collabot> Meeting ended Wed May  8 14:20:19 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[07:20] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-08-13.03.html
[07:20] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-08-13.03.txt
[07:20] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-08-13.03.log.html

2019-05-01 Integration Weekly Meeting

[07:04] == collabot changed the topic of #onap-int to:  (Meeting topic: Integration Testing Friday, 10/13/2017)
[07:04] <@collabot> Meeting ended Wed May  1 14:04:25 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[07:04] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-01-13.10.html
[07:04] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-01-13.10.txt
[07:04] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-05-01-13.10.log.html

2019-04-24 Integration Weekly Meeting

(16:08:11) collabot: Meeting ended Wed Apr 24 14:08:11 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:08:11) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-24-13.01.html
(16:08:11) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-24-13.01.txt
(16:08:11) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-24-13.01.log.html

2019-04-17 Integration Weekly Meeting

[10:18] <@collabot> Meeting ended Wed Apr 17 14:18:30 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[10:18] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-17-13.32.html
[10:18] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-17-13.32.txt
[10:18] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-17-13.32.log.html

Andrew Fenner's network slicing Presentation and Brian's multiple region set up Robot change (starting from 2:30)  Network Slicing Presentation.mp4

2019-04-10 Integration Weekly Meeting

[06:54] == collabot changed the topic of #onap-int to:  (Meeting topic: Integration Testing Friday, 10/13/2017)
[06:54] <@collabot> Meeting ended Wed Apr 10 13:54:15 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[06:54] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-10-13.02.html
[06:54] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-10-13.02.txt
[06:54] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-10-13.02.log.html

Meeting recording with Krzysztof demo of PNF simulator (demo starting at 16:25) 2019-04-10.mp4

2019-04-03 Integration Weekly Meeting

(15:38:51) collabot: Meeting ended Wed Apr 3 13:38:57 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(15:38:51) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-03-13.01.html
(15:38:51) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-03-13.01.txt
(15:38:51) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-04-03-13.01.log.html

2019-03-27 Integration Weekly Meeting

(14:51:24) collabot: Meeting ended Wed Mar 27 13:51:29 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(14:51:24) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-27-13.00.html
(14:51:24) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-27-13.00.txt
(14:51:24) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-27-13.00.log.html

2019-03-20 Integration Weekly Meeting

[06:53] <@collabot> Meeting ended Wed Mar 20 13:53:05 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[06:53] <@collabot> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-20-13.03.html
[06:53] <@collabot> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-20-13.03.txt
[06:53] <@collabot> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-20-13.03.log.html

2019-03-13 Integration Weekly Meeting

(15:12:50) collabot: Meeting ended Wed Mar 13 14:12:55 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(15:12:50) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-13-13.08.html
(15:12:50) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-13-13.08.txt
(15:12:50) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-13-13.08.log.html

2019-03-06 Integration Weekly Meeting

(16:04:06) collabot: Meeting ended Wed Mar 6 15:04:04 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:04:06) collabot: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-06-14.00.html
(16:04:06) collabot: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-06-14.00.txt
(16:04:06) collabot: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-03-06-14.00.log.html

2019-02-27 Integration Weekly Meeting

(16:03:32) collabot`: Meeting ended Wed Feb 27 15:03:34 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:03:32) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-27-14.00.html
(16:03:32) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-27-14.00.txt
(16:03:32) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-27-14.00.log.html

2019-02-20 Integration Weekly Meeting

(16:04:20) collabot`: Meeting ended Wed Feb 20 15:04:24 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:04:20) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-20-14.04.html
(16:04:20) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-20-14.04.txt
(16:04:20) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-20-14.04.log.html

Don't break the build Dublin plan.pptx

2019-02-13 Integration Weekly Meeting

(16:02:34) collabot`: Meeting ended Wed Feb 13 15:02:38 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:02:34) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-13-14.02.html
(16:02:34) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-13-14.02.txt
(16:02:34) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-13-14.02.log.html

recording for Marco's CL design demo and Morgan's tagging scheme presentation (starting at 18:01)

2019-02-06 Integration Weekly Meeting

(16:08:40) collabot`: Meeting ended Wed Feb 6 15:08:40 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:08:40) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-06-14.02.html
(16:08:40) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-06-14.02.txt
(16:08:40) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-02-06-14.02.log.html

2019-01-30 Integration Weekly Meeting

[06:47] <@collabot`> Meeting ended Wed Jan 30 14:47:38 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[06:47] <@collabot`> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-30-14.03.html
[06:47] <@collabot`> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-30-14.03.txt
[06:47] <@collabot`> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-30-14.03.log.html


2019-01-23 Integration Weekly Meeting

(16:04:46) collabot`: Meeting ended Wed Jan 23 15:04:52 2019 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
(16:04:46) collabot`: Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-23-14.02.html
(16:04:46) collabot`: Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-23-14.02.txt
(16:04:46) collabot`: Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-23-14.02.log.html


2019-01-16 Integration Weekly Meeting

[06:50] <@collabot`> Meeting ended Wed Jan 16 14:50:33 2019 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
[06:50] <@collabot`> Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-16-14.02.html
[06:50] <@collabot`> Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-16-14.02.txt
[06:50] <@collabot`> Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2019/onap-int.2019-01-16-14.02.log.html


2019-01-02 Integration Weekly Meeting

  1. Last week's followup
  2. Directories for Orange code contribution (postman collection, python lib, CI). Will discuss with Gary when he comes back
  3. Discuss ONAP CI demo schedule (soon after Paris conference)
  4. Maintenance release update from the team
  5. Paris integration meeting topic (use case development, maintain and add more use cases to CI, new OOM feature, S3P, test management, automated contract testing, separated project for component and CSIT tests). 
  6. Lab resource consolidation (proposal to group projects together as closed loop, and reduce each project resource).
  7. Committer nomination (Brian freeman, HuangZhongHe from China Telecom, Krzywka Filip from Nokia). Suggest to get nomination consensus within represented company first. 


2018-12-19 Integration Weekly Meeting

Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-19-14.09.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-19-14.09.txt
Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-19-14.09.log.html


2018-12-05 Integration Weekly Meeting

Minutes:    http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-05-14.06.html

Minutes (text)http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-05-14.06.txt

Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-12-05-14.06.log.html


2018-11-28 Integration Weekly Meeting

Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-28-14.03.html
Minutes (text)http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-28-14.03.txt
Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-28-14.03.log.html


2018-11-21 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-21-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-21-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-11-21-14.02.log.html

Integration Weekly Meeting Nov. 21, 2018.mp4

2018-11-14 Integration Weekly Meeting

minutes.11142018.txt | meeting.chat.11142018.txt

zoom11142018.mp4


2018-11-07 Integration Weekly Meeting

integratio-meeting-20181107.mp4


2018-10-25 Integration work session

worksession10252018.mp4

worksession10252018.txt


2018-10-24 Integration Working Session

Integration Working Session Oct. 24, 2018.mp4

Integration Working Session (2).mp4

2018-10-24 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-24-14.01.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-24-14.01.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-24-14.01.log.html

Integration Weekly Meeting October 24, 2018.mp4


2018-10-17 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-17-14.13.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-17-14.13.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-17-14.13.log.html

Integration Weekly Meeting Record October 17, 2018.mp4

2018-10-10 Integration Weekly Meeting

Meeting ended Wed Oct 10 16:03:33 2018 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-10-14.01.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-10-14.01.txt

Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-10-10-14.01.log.html

demo-onap-tests

Integration Weekly Meeting Record October 10, 2018.mp4


2018-10-03 Integration Weekly Meeting

Minutes (text) 10032018minutes.txt

Recording: zoom_0.mp4chat.txt

2018-09-26 Integration Weekly Meeting

Meeting ended Wed Sep 26 16:12:38 2018 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-26-14.00.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-26-14.00.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-26-14.00.log.html

Integration Weekly Meeting Recording September 26, 2018.mp4

2018-09-19 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-19-14.01.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-19-14.01.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-19-14.01.log.html

2018-09-12 Integration Weekly Meeting
Meeting ended Wed Sep 12 15:01:12 2018 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-12-14.04.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-12-14.04.txt
Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-12-14.04.log.html


2018-09-05 Integration Weekly Meeting

Meeting ended Wed Sep 5 15:29:27 2018 UTC. Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-05-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-05-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-09-05-14.02.log.html

Integration Weekly Meeting Recording September 05,2018.mp4

2018-08-29 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-29-14.04.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-29-14.04.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-29-14.04.log.html

Integration Weekly Meeting Recording August 29, 2018 (Part I).mp4

Integration Weekly Meeting Recording August 29, 2018 (Part 2)(CIA).mp4


2018-08-22 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-22-14.01.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-22-14.01.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-22-14.01.log.html

Integration Weekly Meeting Recording August 22, 2018.mp4

2018-08-15 Integration Weekly Meeting

 Meeting ended Wed Aug 15 15:09:28 2018 UTC.  Information about MeetBot at http://wiki.debian.org/MeetBot . (v 0.1.4)
Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-15-14.03.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-15-14.03.txt
Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-15-14.03.log.html


2018-08-08 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-08-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-08-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-08-14.02.log.html

Status for CIA project 2018-08-08

Integration Weekly Meeting Record August 8, 2018.mp4


2018-08-01 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-01-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-01-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-01-14.02.log.html

Integration Weekly Meeting Record August 1, 2018.mp4

2018-07-25 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-25-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-25-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-25-14.02.log.html

Integration Weekly Meeting Minutes July 25, 2018.mp4

2018-07-18 Integration Weekly Meeting

Minutes: Integration Weekly Meeting Minutes, July 18 2018

2018-07-11 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-11-14.03.html
8:04 AM Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-11-14.03.txt
8:04 AM Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-07-11-14.03.log.html

Integration Weekly Meeting Record 7-11-2018.mp4

2018-06-12 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-06-12-14.01.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-06-12-14.01.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-06-12-14.01.log.html

Integration Weekly Meeting Recording June 12 2018.mp4

2018-06-05 Integration Weekly Meeting

Integration Weekly Meeting Recording June 5th.mp4

2018-05-15 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-05-15-14.05.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-05-15-14.05.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-05-15-14.05.log.html

2018-05-13 Integration Stability Testing Kickoff Session

ONAP Platform Stability Testing with HEAT kickoff Session.mp4

2018-04-18 Projects Pair Wise Testing Review Session

Projects Pair Wise Testing Review Session.mp4

2018-04-17 Integration Testing Session

OOM Basic Command Training Session Record.mp4

K8S / helm basic commands for ONAP integration

2018-04-17 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-17-14.03.html
Minutes (text): http://OOM Basic Command Training Session Record.mp4.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-17-14.03.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-17-14.03.log.html

Integration Weekly Meeting Recording Apr 17.mp4

2018-04-13 Integration Testing Session

Integration Working Session (OOM) 2018-04-13.mp4

chat.txt

2018-04-11 Integration Testing Session

Integration Working Session (OOM) 2018-04-11.mp4

2018-04-10 Integration Testing Session

Integration Working Session (OOM) 2018-04-10.mp4

2018-04-10 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-10-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-10-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-10-14.02.log.html

Integration Weekly Meeting Recording Apr 11, 2018.mp4

2018-04-09 Integration Testing Session

Integration Working Session (OOM) 2018-04-09.mp4

2018-04-03 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-03-14.02.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-03-14.02.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-04-03-14.02.log.html

2018-03-27 Integration Weekly Meeting

Minutes:        http://ircbot.wl.linuxfoundation.org/meetings/onap-meeting/2018/onap-meeting.2018-03-27-14.00.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-meeting/2018/onap-meeting.2018-03-27-14.00.txt
Log:            http://ircbot.wl.linuxfoundation.org/meetings/onap-meeting/2018/onap-meeting.2018-03-27-14.00.log.html

3/13/2018 Test Report Technical Discussion

Test Report Technical Discussion.mp4

3/13/2018  Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-13-14.00.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-13-14.00.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-13-14.00.log.html

Video includes Locust Demo:

Integration Weekly Meeting Recording March 13.mp4

3/12/2018

Testing Report demo and discussion.mp4

3/6/2018 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-06-15.39.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-06-15.39.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-03-06-15.39.log.html

Video includes JMeter Demo:

Integration Weekly Meeting Recording March 06 (JMeter).mp4

2/27/2018 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-27-14.31.html
http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-27-14.31.txt
http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-27-14.31.log.html


2/20/2018 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-20-14.34.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-20-14.34.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-20-14.34.log.html

2/13/2018 Integration Weekly Meeting

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-13-14.31.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-13-14.31.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-02-13-14.31.log.html

integration_demo_E2E_chain.pdf

Integration Weekly Meeting Recording Feb 13.mp4

2/6/2018

  • vF2F meeting - no team meeting

1/30/2018

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-30-14.30.html
7:53 AM Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-30-14.30.txt
7:53 AM Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-30-14.30.log.html

Integration Weekly Meeting Recording Jan 30 2018.mp4

1/23/2018

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-23-14.31.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-23-14.31.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-23-14.31.log.html

Integration Weekly Meeting Recording Jan 23, 2018.mp4

ONAP Integration Beijing Release.pdf

1/16/2018

Minutes: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-16-14.31.html
Minutes (text): http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-16-14.31.txt
Log: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-01-16-14.31.log.html

Integration Weekly Meeting Recording Jan 16, 2018.mp4


1/3/2018 Integration Weekly Meeting Minutes Jan 03, 2018

12/20/2017 Integration Weekly Meeting Minutes Dec 20, 2017

12/13/2017 Meeting at Face to Face: Integration Meeting Minutes 2017-12-13 Face to Face


12/06/2017: http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2017/onap-int.2017-12-06-14.33.html


11/21/2017

Integration Weekly Meeting Recording Nov 21st 2017.mp4

10/30/2017

DCAE_MultiCloud Integration Testing.mp4

10/05/2017 

Integration Testing 10052017.mp4

Integration Testing 10052017.txt

10/04/2017

IntegrationTesting20171004.mp4

IntegrationTesting20171004.txt

9/21/2017

OpenStack Version Discussion.mp4

OpenStack Version Discussion Meeting Minutes

9/19/2017

ONAP installation via Heat.mp4

Integration Weekly Meeting Recording September 19th.mp4

Integration Weekly Meeting Minutes September 19th

9/12/2017

Integration Weekly Meeting Recording September 12th.mp4

Meeting Minutes 9/12/2017

9/5/2017

Integration Weekly Meeting Recording September 5th.mp4.mp4

8/29/2017

Integration Weekly Meeting Recording August 29th.mp4

8/22/2017

Meeting Minutes 8/22/2017

Integration Weekly Meeting Recording August 22th.mp4

8/17/2017


Brief: Eric presented his practice in Orange lab on how to deploy ONAP and onboarding VNFs

Eric's YAML file

Automating the onboarding VNF and service modeling using SDC API.mp4

8/15/2017

Integration Weekly Meeting Minutes, August 15th, 2017

Integration Weekly Meeting Recording August 15th.mp4

8/10/2017

E2E Use Case Lab Implementation Discussion Minutes

E2E Use Case Lab Implementation Discussion Recording

8/8/2017

Integration Weekly Meeting Record August 8th, 2017

8/1/2017

integration-meeting-notes-20170718.txt

Integration Weekly Meeting Record August 1, 2017

7/18/2017:

Meeting notes

CSIT Training

7/11/2017:

Meeting notes

6/27/2017:

Meeting notes

Meeting Record

6/20/2017:

  1. Logistic check:
    1. LF ID, etc..
    2. gerrit
    3. JIRA: 
    4. etc.
  2. Integration V1 Release Plan
  3. Group Integration into subcategories


  • No labels