The page is intended to summarize all the requirements for Dublin Release.

These requirements have been prioritized by the TSC  to realistically fit within the Dublin Release Timeline.

This is not yet the Dublin Release scope. Release Scope will be finalized during the M1 Release Planning.

Projects intended to participate within Dublin release are posted in wiki.

New projects proposal are posted here. These projects need to be reviewed and approved by TSC.

Some of the Use Cases, Functional and non functional requirements are carried over from previous releases as they required multiple releases to be implemented.

The Requirements extracted from SP lists of priorities for Dublin are covered either by the Use Case, the functional requirements, the non functional requirement or within a project scope of work.

  • Use Cases 
  • Functional Requirements 
  • Non Functional Requirements 

TSC Prioritization (Ranking)

  • RANK #0  – Special GO - fully covered by involved companies
  • RANK #1  – GO “Must Have”
  • RANK #2 - GO “Continuity of previous releases”
  • RANK #3 – GO if PTLs are OK since the impacted applications are less “stretched” i.e. CLAMP, Policy, DCAE etc.
  • RANK #4 – NO GO – Mostly new requirements/features/projects

Use Cases 

M1 Scorecard:

  • Green: Use Case will be fully implemented and tested
  • Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
  • Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Priority

M1

Scorecard

TSC M1 ApprovalUse CaseOwnerProjects or functional requirements impacted for DublinLink(s) to HLD/LLD if anyDependency (from/to) another project(s)

T-Shirt Size (star)

Project's Impact: Test Only (TO), Code (C)Committed (C)/ Partially Committed (P) or not (N) per impacted projectIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)

Company

Engagement

NotesM4 Status

1-regression

3-enhancements



vFW

Policy/(APPC)

HPA

vFirewall Use Case Upgrade
XS

All: Test Only except Policy

APPC(TO)

Policy: Committed


Policy: Committed

AT&T

1

vDNSIntegration TeamHPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


1

VoLTE

Integration Team

HPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


1

vCPE with or without TOSCAIntegration TeamHPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


2

CCVPN Use Case(Dublin)   High priority:1, SD-WAN Multi-site to Multi-site service creation; 2, Service change: add or delete a site;3, close loop intelligent surveillance

SDC, SO, SDN-C,OOF,ExternalAPI, UUI, ESR,Modeling,MultiVIM/Cloud, VFC, Modeling, DCAE, Policy, Holmes,

Consistent ID of a cloud region

CCVPN Use Case (Dublin)
AAI: M

AAI: TO

DCAE: TO

ExtAPI: TO

Multi-VIM: Test support

Holmes: C

SDC: Partially committed based on Chinamobile/ZTE/Vodafone contribution

SO: Committed based on the contributions from CMCC, ZTE and VDF for the main flows

SDN-C/CCSDK : Committed based on contributions from Huawei and ZTE

VF-C: Committed

Modeling: Committed

Usecase-UI: Committed

Holmes: Committed based on Huawei and ZTE contribution

Multi-VIM/Cloud: Committed based on VMware contribution

Policy: Committed base on Huawei contribution

ExtAPI: Committed as long as a serviceOrder is created, either for service creation or modification with full service characteristics and values. ExtAPI can not read service characteristic and service state from AAI which does not expose those informations.

SDC: not enough resources

Dev/Test privided by Chinamobile, Vodafone, Huawei,

ZTE, WindRiver, VMWare, Intel, Lenovo, ChinaTelecom, Fujitsu



2

5GSDC, SO, VNFSDK, AAI, DCAE, SDNC,CCSDK,VID, PORTAL, AAI/ESR, VFC, APPC, DMaaP, Policy5G Use Case
AAI: M

SDC: Committed based on Nokia/Ericsson/Amdocs contribution

DCAE: Committed based on Ericsson contribution for 5G - Bulk PM (Casablanca carry-over items)  and Wipro  contribution on - 5G - OOF and PCI

SO: Committed based on the contributions from Nokia (to be confirmed)
PNF configuration committed from Nokia (some CDS dependencies)

AAI: Partially committed

CCSDK/SDN-C : Committed to Tosca ingest changes
NETCONF configuration committed from Ericsson (some CDS dependencies)

PORTAL: Partial committed

VID: Partial committed

Policy: Committed based on wipro contribution

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

PORTAL: Targets only the top menu integration required for 5G use case functions from VID and SDC/AAI

VID: No enhancements dev


 - Benjamin Cheung I added policy because my understanding from N.K. Shankaranarayanan there are additions for 5G - OOF and PCI


0

BBSDavid Perez CaparrosDCAE, ExternalAPI, Modeling, SDNC, SOBBS Broadband Service Use Case (Dublin)PRH - 5G Use Case

AAI:
(using 5G use case PNF discovery and re-registration: TO (to be confirmed)

DCAE: C

ExtAPI: C

SDC: TO

SO (using 5G use case PNF discovery and re-registration): TO

Policy: TO

CLAMP: TO

SDNC: C

Modeling: design


DCAE: Committed based on contribution from Huawei, TechM and Nokia

ExternalAPI: Committed

SO: 5G PNF Committed based on the contributions from Nokia /Huawei

SDNC: Committed based on contributions from BBS team

Modeling: contributions from Swisscom/Huawei/Nokia


AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability


Nokia, Swisscom, Huawei,
TechM



(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Functional Requirements

M1 Scorecard:

  • Green: The functional requirement will be fully implemented and tested
  • Yellow:  The functional requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
  • Red: The functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
PriorityM1 ScorecardTSC M1 ApprovalFunctional RequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)Company EngagementNotesM4 Status
2

Consistent ID of a Cloud Region (Dublin)Bin YangSDNC & APPC , VID, SO, UUI, VFC, OOFConsistent ID of a Cloud Region (Dublin)

APPC(TO, code already exists),

SDN-C: test support only

SO: Support testing effort, changes are likely in.

VFC:Committed

UUI:Committed

VID: Committed based on ATT resources


AT&T

China Mobile



2

Continuation of HPA (Dublin)Alexander VulComponents used by vFW, vDNS, vCPE, VoLTEContinuation of HPA (Dublin)

AAI: TO

SO: Code Hardening, Expansion of use-case support, testing


AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability


2

Scaling Use Case (Dublin)Scott BlandfordMain focus on DCAE/CLAMP & PolicyScaling Use Case (Dublin)


CLAMP: Committed (Based on TechM resource commitment)

Policy: Committed (Based on TechM Resource Commitment)





0

K8S based Cloud Region SupportMulti-Cloud, AAI, SDC, SOK8S based Cloud Region Support

AAI: TO

SDC & SO: Committed based on Intel/VMWare contribution

AAI: Partially committed

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

Intel, VMWare

3

Distributed Analytics as a Service (Dublin Summary) - Edge Automation

Multi-Cloud, Demo


Distributed Analytics as a Service (Dublin Summary) - Edge Automation


MultiVIM/Cloud: partially committed based on VMware's contribution
VMware

2

Change Management Dublin ExtensionsAjay MahimkarAPPC, SDNC, OOF, Policy, A&AI, SDC, SO, VIDChange Management Dublin Extensions

APPC (C), OOF (C), Policy (TO), A&AI (TO), SDC (TO), VID (C) 

APPC: Committed (Orange for Traffic Migration)

OOF: Committed (Orange for Traffic Migration, and AT&T for Schedule Optimization)

Policy: test only - per Ajay no need for dev for this release

A&AI - test only

SDC - test only

SO: Partially committed based on AT&T resources (for Flexible designer and orchestrator)

VID: Committed based on Nokia resources- pending final decision

SDC: not enough resources, stretch goal

SDNC: stretch goal (Ericsson for 5G Software Upgrade using NetConf)

SO: Scope of the changes and effort to be estimated.

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

OOF:

  • Traffic Migration Workflow Resources from Orange
  • Schedule Optimization with Automated Conflict Avoidance (adjusting scope based on resource commitments)

Orange,

AT&T,

Ericsson



3

Model Driven Control Loop Design (Close Loop sub-committee)DCAE, CLAMP, Policy

Model driven Control Loop Design





DCAE: AT&T Committed

CLAMP: Committed

Policy: Committed

AT&T commits to finding the required resources

AT&T, Nokia

3

Self Serve Control Loop (Closed Loop Subcommittee)  Scott BlandfordDCAE, Policy, SDC

Model driven Control Loop Design

This is a stretch goal for Dublin.  We are still trying to align resources so that this can be accomplished this release

   

 DCAE: Stretch Goal

Policy: Stretch Goal

SDC: Stretch Goal

DCAE Resource constraints

Policy: Resource Constraints

SDC: Resource Contrstraints

AT&T  
3

Fine-Grained Placement Service (F-GPS)Multi-Cloud, OOF

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2

F-GPS (Dublin Summary)




OOF: Committed

MultiVIM/Cloud: Committed

End-to-end Use Case Integration: Stretch Goal (due to several workflow changes)


IBM, AT&T, VMware (Architecture/Modelling), Intel (Architecture), 



3

Modularity

SO, SDC, VFC, APPC, SDNC

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


SDC: Not committed

APPC: Not committed

SO: Committed based on the code from R3

SDNC: Not committed

VFC: Partially committed

SDC: no resources, not enough info

APPC: no resources

SDNC: no resources

VFC: optimize DB microservice




3

ETSI Alignment (SO plug-in)SO, SDC, AAI, External APIhttps://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


SDC: Partially committed (based on Ericsson contribution)

SO: Committed (SOL003) based on contribution from Nokia and Ericcson

AAI: Not Committed

SDC: no resources

SO: SOL005 Under discussion with Verizon.

AAI: no resources




4

OSAM/PNF??????







4

TOSCA Task Force???https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


OOF: Policy Tosca model API and ONAP CLI integrationIntel


4

Alloted Network Function??????







 3

 VSP Compliance Check SDC VSP Compliance Check within SDC (Dublin)    SDC: Committed based on contribution from VF, Huawei and Iconnectiv

 Vodafone, iconectiv, huawei

   

(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Non-Functional Requirements

M1 Scorecard:

  • Green: The non-functional requirement will be fully implemented and tested
  • Yellow: The non-functional requirement will be partially implemented. It is possible to identify capabilities for this non-functional requirement can be tested (phasing approach).
  • Red: The non-functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
PriorityM1 Scorecard

TSC M1

Approval

Non Functional RequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)Company EngagementNotesM4 Status
1

Improve our E2E Process Automation

SO
SDC
CCSDK
OOM
Testsuite
Documentation

AAI
AAF
DMaaP
Policy

PNF use case (5G)
XL

Code:
SO
SDC
CCSDK
OOM
Testsuite

APPC (CDS)

TO:
AAI
DMaaP
Policy


SDC:
TechM (C)
IBM (C)

CCSDK:
ATT (C)
Bell   (C)
IBM (C)
Ericsson (C)
TechM (C)

SO:
Ericsson (C)
Bell (C)
ATT (P)

OOM:
Orange (P)
Bell (C)

Testsuite:
Orange (C)
Huawei (C)
Dutch T (C)

Documentation:
Orange (C)
Bell (C)
Dutch T (C)

AAI: TO


AT&T
Bell Canada
Ericsson
Huawei
IBM
Orange
Tech Mahindra



1

S3P - Footprint OptimizationOOM + ALLhttps://wiki.onap.org/download/attachments/45293323/Dublin-Footprint-Optimizations.pdf?version=1&modificationDate=1544543600000&api=v2


SDC: N

CCSDK, CLAMP: Committed

Multi-VIM/loud: committed

Policy: committed

SDC: no resources


1

CI/CD

Infrastructure


TSC-25 - Getting issue details... STATUS

Integration

Logging

OOM

Lno

OOM:

Bell (C)

Amdocs (C)

Logging:

Bell (C)

Amdocs (C)

Integration:





1

Document as You CodeALLTracked in JIRA - Label: Documentation







1

Security by DesignSecurity SubcommitteeALL

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Security%20-%20Requirements-pa2.pptx?version=1&modificationDate=1544453068000&api=v2









1

Modeling M3 Checklist enhancementModeling SubcommitteeSO, SDC, VFC, APPC, VNFSDKProposed M3 Checklist modeling updates discussion


VFC: Committed



1

S3P - Provide Upgrade CapabilitiesOOM + ALLDublin Release Platform Maturity


CLAMP: Committed



1

Move Helm Chart (OOM) at project levelOOM + ALL



During the PTL meeting on 12/17 -it was agreed that

No enforcement to make it happen for all project in Dublin release, but expectation to to completed within El Alto release. This could potentially be a S3P items.

6 projects have been identified for trial: Logging, Policy, APPC, CLAMP, AAI and ONAP CLI




1

oParent Integration to fix vulenaribilities

Security Subcommitee

Yang Xu

Integration +ALL



AAI, DCAE, DMaaP, Holmes, Logging, MSB, Multi-Cloud, ONAP CLI, UUI, Policy, Portal, SO, VFC, VNFSDK, AAF,CLAMP, MUSIC: Already Integrated

ExtApi, VID: Committed

SDC: Not Committed

Modeling?

CCSDK/SDNC, OOM, APPC, OOM: No

CCSDK/SDNC, APPC: dependency on ODL

OOF (HAS, OSDF): python, not Java

SDC: No resource

OOM: No java code





1

CIST running OOMPTLsNeed to assess
Infrastructure capacity






2

S3P- Geo-RedundancyOOM/MUSIC Integration to ONAP ComponentsDublin Release Platform Maturity







2

SOL 004 (VNF Package Security)Samuli KuuselaSDC, VNFSDK(?)



SDC: Partially committed (based on Ericsson contribution)



3

xNF communication security enhancementsAAF, DCAE, ControllersSlide presented on PTL Call (1/14/2019)


DCAE - Committed based on Nokia's contribution
Controller part (SDNC) committed from Ericsson, see 5G UC





4

S3P - Service Mesh (ISTIO)Security & Architecture SubcommitteesALL except MSB or performed at K8S level (OOM); Poc of ISTIO plug-in to AAF not resourcedhttps://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2







4

S3P Manageability - Logging Capabilities

see yellow/red in

in progress

log, aaf cli, consul, contrib, dcae, dmaap, nbi, oof, sdnc, so, uui, vid, vnfsdk, vvp

good

aai, appc, clamp, esr, multicloud, policy, pomba, portal, sdc, vfc


???







3

Locale/Internationalization language supportPortal, UsecaseUIInternationalization language supportPortal, UsecaseUIL

Code:
PORTAL, UsecaseUI

UsecaseUI (C)



3

Angular 6 Upgrade of ONAP Portal and SDKPortal

PORTAL-330 - Getting issue details... STATUS

PortalXL

Code:

PORTAL

TO:

Policy, VID

PORTAL (C)



(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.
  • No labels