The page is intended to summarize all the requirements for Dublin Release.

These requirements have been prioritized by the TSC  to realistically fit within the Dublin Release Timeline.

This is not yet the Dublin Release scope. Release Scope will be finalized during the M1 Release Planning.

Projects intended to participate within Dublin release are posted in wiki.

New projects proposal are posted here. These projects need to be reviewed and approved by TSC.

Some of the Use Cases, Functional and non functional requirements are carried over from previous releases as they required multiple releases to be implemented.

The Requirements extracted from SP lists of priorities for Dublin are covered either by the Use Case, the functional requirements, the non functional requirement or within a project scope of work.

  • Use Cases 
  • Functional Requirements 
  • Non Functional Requirements 

TSC Prioritization (Ranking)

  • RANK #0  – Special GO - fully covered by involved companies
  • RANK #1  – GO “Must Have”
  • RANK #2 - GO “Continuity of previous releases”
  • RANK #3 – GO if PTLs are OK since the impacted applications are less “stretched” i.e. CLAMP, Policy, DCAE etc.
  • RANK #4 – NO GO – Mostly new requirements/features/projects

Use Cases 

M1 Scorecard:

  • Green: Use Case will be fully implemented and tested
  • Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
  • Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Priority

M1

Scorecard

TSC M1 ApprovalUse CaseOwnerProjects or functional requirements impacted for DublinLink(s) to HLD/LLD if anyDependency (from/to) another project(s)

T-Shirt Size (star)

Project's Impact: Test Only (TO), Code (C)Committed (C)/ Partially Committed (P) or not (N) per impacted projectIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)

Company

Engagement

NotesM4 Status

1-regression

3-enhancements

HPA Testing confirmed by INTELYvFW

Policy/(APPC)

HPA

vFirewall Use Case Upgrade
XS

All: Test Only except Policy

APPC(TO)

Policy: Committed


Policy: Committed

AT&T

1HPA HPA Testing confirmed by INTELYvDNSIntegration TeamHPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


1Not part of Dublin scope - no regression testNA

Integration Team

HPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


1Not part of Dublin scope - no regression testNA
Integration Team



All: Test OnlyN/A - part of regression testsN/A - part of regression tests


1

HPA Testing confirmed by INTEL 

YvCPE (Heat)Integration TeamHPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


2Davide/Lin to review and provide final feedbackY (conditional)CCVPN Use Case (Dublin)   High priority:1, SD-WAN Multi-site to Multi-site service creation; 2, Service change: add or delete a site;3, close loop intelligent surveillance

SDC, SO, SDN-C,OOF,ExternalAPI, UUI, ESR,Modeling,MultiVIM/Cloud, VFC, Modeling, DCAE, Policy, Holmes,

Consistent ID of a cloud region

CCVPN Use Case (Dublin)
AAI: M

AAI: TO

DCAE: TO

ExtAPI: TO

Multi-VIM: Test support

Holmes: C

SDC: Partially committed based on Chinamobile/ZTE/Vodafone contribution

SO: Committed based on the contributions from CMCC, ZTE and VDF for the main flows

SDN-C/CCSDK : Committed based on contributions from Huawei and ZTE

VF-C: Committed

Modeling: Committed

Usecase-UI: Committed

Holmes: Committed based on Huawei and ZTE contribution

Multi-VIM/Cloud: Committed based on VMware contribution

Policy: Committed base on Huawei contribution

ExtAPI: Committed as long as a serviceOrder is created, either for service creation or modification with full service characteristics and values. ExtAPI can not read service characteristic and service state from AAI which does not expose those informations.

SDC: not enough resources

Dev/Test provided by Chinamobile, Vodafone, Huawei,

ZTE, WindRiver, VMWare, Intel, Lenovo, ChinaTelecom, Fujitsu



25G Use Case (Dublin)Y

5G: PNF

Pre-onboarding

Onboarding

SDC, VNFSDK, VNFRqmt (Docs)5G - PNF Pre-Onboarding & OnboardingBBS

SDC: C

VNFSDK: C

SDC: Committed based on Nokia/Ericsson contribution

VNFSDK: Committed


AT&T, Huawei, Ericsson, NokiaPNF POB/OB U/C is now in development, requirements and architecture stage with high corporate commitment.
25G Use Case (Dublin)Y5G: Bulk PMDCAE, DMaaP, VNFRqmt5G - Bulk PM (Casablanca carry-over items)5G: PM Dictionary

DCAE: C

DMaaP: C


DCAE: Committed based on Ericsson contribution

DMaaP: Committed


AT&T, Ericsson, NokiaBulk PM is in development with high corporate commitment.
25G Use Case (Dublin)Y5G: Config w/ NetConfOskar MalmSDC, (VID), SO, SDNC, CCSDK, VNFRQTS5G - Configuration with NETCONF

5G: PNF PnP

e2e automation


SDC: C

(VID)

SO: C

SDNC: C

CCSDK: C

SDNC: NETCONF/TLS support in controller committed from Ericsson

Additional development (SDC, SO, CCSDK) for PNF configuration UC is coordinated with CDS / e2e automation. See separate row for details.

PNF configuration testing: Ericsson

SO: (not a separate initiative uses E2E automation) assign/config building block


AT&T, EricssonNetConf is in development with high corporate commitment
25G Use Case (Dublin)Y5G: FM Meta PM DictionarySDC, VNFRqmt, VES Specification (Done)5G - FM Meta Data / 5G - PM Dictionary

5G: Bulk PM

5G: PNF OB


SDC: CSDC: Commit
AT&T, Ericsson, NokiaFMPM Dictionary is in development with high corporate commitment
25G Use Case (Dublin)Y (Conditional)5G: OOF & PCISDC, APP-C, DCAE, OOF, Policy, VNFRqmt5G - OOF and PCI (Casablanca carry-over items)

5G: PNF OB

Control Loop U/C


SDC: C

SDN-C: C

DCAE: C

OOF: C

Policy: C

SDC: NEED REVIEW

SDN-C: Commit

DCAE: Committed based on Wipro contribution

OOF: Commit

Policy: Committed based on Wipro contribution


AT&T, Wipro, Tech Mahindra

OOF/PCI Enhancements is in development with high corporate commitment

Dublin Release Requirements I added policy because my understanding from Dublin Release Requirements there are additions for 5G - OOF and PCI


25G Use Case (Dublin)Y (Conditional)5G: PNF Plug and Play & PNF Re-registrationBenjamin CheungSDC, Portal, VID, SO, A&AI, SDN-C, DCAE5G - PNF Plug and Play (Casablanca carry-over items)BBS

SDC: C

Port: C

VID: C

SO: C

A&AI: C

SDN-C: C

DCAE: C

AAF: C

Portal: Commit

VID: Reviewing

SO: Committed based on the contributions from Nokia (confirmed)

A&AI: Commit

CCSDK/SDN-C : Committed to Tosca ingest changes

DCAE: Committed based on the contributions from Nokia

AAF: Commit

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability (Jan 30 James Forsyth has ok'ed A&AI commitment)

PORTAL: Targets only the top menu integration required for 5G use case functions from VID and SDC/AAI

VID: No enhancements dev

AT&T, Huawei, Ericsson, NokiaPNF PNP Enhancements is in development with high corporate commitment
25G Use Case (Dublin)Y5G: Network SlicingBorislav GlozmanSDC, Modeling Sub-committee5G - Slicing

SDC: C

Model: TO

SDC: Commit

Model: Commit


AT&T, Amdocs, EricssonNetwork Slicing has only modeling work that is being done in R4.
0
#action (Chaker): Add a risk concerning dependenecy with 5G Use CasesBBSDavid Perez CaparrosDCAE, ExternalAPI, Modeling, SDNC, SOBBS Broadband Service Use Case (Dublin)PRH - 5G Use Case

AAI:
(using 5G use case PNF discovery and re-registration: TO

DCAE: C

ExtAPI: C

SDC: TO

SO (using 5G use case PNF discovery and re-registration): TO

Policy: TO

CLAMP: TO

SDNC: C

Modeling: design


DCAE: Committed based on contribution from Huawei, TechM and Nokia

ExternalAPI: Committed

SO: 5G PNF Committed based on the contributions from Nokia /Huawei

SDNC: Committed based on contributions from BBS team

Modeling: contributions from Swisscom/Huawei/Nokia


AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability


Nokia, Swisscom, Huawei,
TechM



(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Functional Requirements

M1 Scorecard:

  • Green: The functional requirement will be fully implemented and tested
  • Yellow:  The functional requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
  • Red: The functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
PriorityM1 ScorecardTSC M1 ApprovalFunctional RequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)Company EngagementNotesM4 Status
2

#action - Need to confirm testing resource to Yang Xu and what they will be able to test

Bin/Yang to sync-up

Consistent ID of a Cloud Region (Dublin)Bin YangSDNC & APPC , VID, SO, UUI, VFC, OOFConsistent ID of a Cloud Region (Dublin)

APPC(TO, code already exists),

SDN-C: test support only

SO: Support testing effort, changes are likely in.

VFC:Committed

UUI:Committed

VID: Committed based on ATT resources


AT&T

China Mobile



2HPA Testing confirmed by INTEL


Continuation of HPA (Dublin)Alexander VulVNFSDK, SDC, SO, VF-C, OOF, AAI, Policy, Multi-CloudContinuation of HPA (Dublin)SDC - Jira bugs open, OL001 compatibility requirements addressed.

AAI: TO

SO: Code Hardening, Expansion of use-case support, testing


AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

Intel

ARM(???)

Development t resources from ARM are required to test HPA support on ARM hardware
2

Scaling Use Case (Dublin)Scott BlandfordMain focus on DCAE/CLAMP & PolicyScaling Use Case (Dublin)

DCAE: TO

CLAMP: Committed (Based on TechM resource commitment)

Policy: Committed (Based on TechM Resource Commitment)





0Testing confirmed by INTEL


K8S based Cloud Region SupportMulti-Cloud, AAI, SDC, SOK8S based Cloud Region Support

AAI: TO

SDC & SO: Committed based on Intel/VMWare contribution

AAI: Partially committed

AAI: assuming schema/model changes only contributed by community. Also depends on AAI modelling SME availability

Intel, VMWare

3

POC for Dublin under Multi-Cloud umbrella

Testing confirmed by INTEL


#action for Srini/Marco/Yang - identify another repo than demo

Distributed Analytics as a Service (Dublin Summary) - Edge Automation

Multi-Cloud, Demo


Distributed Analytics as a Service (Dublin Summary) - Edge Automation


MultiVIM/Cloud: partially committed based on VMware's contribution
VMware, Intel

2

SO Only

Testing confirmed by CM Team (AT&T)

#action - Ajay/Seshu/Ryan to meet and provide low level requirements

Change Management Dublin Extensions - Flexible designer/orchestratorSO, VIDChange Management Dublin Extensions

SO (C),

VID (C)

SO: Committed (AT&T)

VID: pending final decision from Nokia (stretch goal)


AT&T

Nokia



2

Testing confirmed by AT&T
Change Management Dublin Extensions - Traffic Migration
APPC, OOFChange Management Dublin Extensions

APPC (C),

OOF (C),

A&AI (TO)

APPC: Committed (Orange)

OOF: Committed (Orange)


Orange



2Testing confirmed by AT&T
Change Management Dublin Extensions - Schedule OptimizationOOFChange Management Dublin Extensions

OOF (C),

Policy (TO)

OOF: Committed (AT&T)
AT&T

3Testing confirmed by AT&T


Model Driven Control Loop Design (Close Loop sub-committee)DCAE, CLAMP, Policy

Model driven Control Loop Design





DCAE: AT&T Committed

CLAMP: Committed

Policy: Committed

AT&T commits to finding the required resources

AT&T, Nokia

3Move to POC
Self Serve Control Loop (Closed Loop Subcommittee)  Scott BlandfordDCAE, Policy, SDC

Model driven Control Loop Design

This is a stretch goal for Dublin.  We are still trying to align resources so that this can be accomplished this release

   

DCAE: Stretch Goal

Policy: Stretch Goal

SDC: Stretch Goal

DCAE Resource constraints

Policy: Resource Constraints

SDC: Resource Contrstraints

AT&T  
3Move to POC
Fine-Grained Placement Service (F-GPS)Multi-Cloud, OOF

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2

F-GPS (Dublin Summary)




OOF: Committed

MultiVIM/Cloud: Committed

End-to-end Use Case Integration: Stretch Goal (due to several workflow changes)


IBM, AT&T, VMware (Architecture/Modelling), Intel (Architecture), 



3

SO Only

Testing confirmed by SO Team


Modularity

SO, SDC, VFC, APPC, SDNC

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


https://jira.onap.org/browse/CCSDK-575




SDC: Not committed

APPC: Not committed

SO: Committed based on the code from R3

SDNC: Not committed

VFC: Partially committed

SDC: no resources, not enough info

APPC: no resources

SDNC: no resources

VFC: optimize DB microservice

CDS project will provide Resource assignment functionality




3

ETSI Alignment

SOOL003 plug-in to SO



ETSI Alignment

SO plugint to support SOL003 to connect to an external VNFM

SO, SDC, AAI,https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


SDC: Partially committed (based on Ericsson contribution)

SO: Committed (SOL003) based on contribution from Nokia and Ericsson

AAI: Not Committed

SDC: no resources

.AAI: no resources (detailed impact to be discussed) Action Byuong





 3

ETSI Alignment.

SOL005 plug-in to SO 

 (yellow or red?) ETSI Alignment

SO plugint to support SOL005 to connect to an external NFVO

 SO, SDC, AA, External API, VFC (underdiscussion)

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


     SO: SOL005 under dicusion with Verizon   
4Architecture did not approve
OSAM/PNF??????







4

TOSCA Task Force???https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2


OOF: Policy Tosca model API and ONAP CLI integrationIntel


4

Alloted Network Function??????







 3
Need to confirm testing resourcePhase 1 - VSP Compliance Check

 SDC

CLI/VNFSDK

 VSP Compliance Check within SDC (Dublin)   SDC: Committed based on contribution from VF, Huawei and iconectiv

Vodafone, iconectiv, huawei

   

(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Non-Functional Requirements

M1 Scorecard:

  • Green: The non-functional requirement will be fully implemented and tested
  • Yellow: The non-functional requirement will be partially implemented. It is possible to identify capabilities for this non-functional requirement can be tested (phasing approach).
  • Red: The non-functional requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
PriorityM1 Scorecard

TSC M1

Approval

Non Functional RequirementOwnerProject ImpactedLink(s) to HLD/LLD if anyDependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL) (star)Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)Company EngagementNotesM4 Status
1Not committed: Ability to instantiate the entire service with API (VID)



Improve our E2E Process Automation

SO
SDC
CCSDK
OOM
Testsuite
Documentation

AAI
AAF
DMaaP
Policy

PNF use case (5G)
XL

Code:
SO
SDC
CCSDK
OOM
Testsuite

APPC (CDS)

TO:
AAI
DMaaP
Policy


SDC:
TechM (C)
IBM (C)

CCSDK:
ATT (C)
Bell   (C)
IBM (C)
Ericsson (C)
TechM (C)

SO:
Ericsson (C)
Bell (C)
ATT (P)

OOM:
Orange (P)
Bell (C)

Testsuite:
Orange (C)
Huawei (C)
Dutch T (C)

Documentation:
Orange (C)
Bell (C)
Dutch T (C)

AAI: TO


AT&T
Bell Canada
Ericsson
Huawei
IBM
Orange
Tech Mahindra



1
  • Container optimization : on –going (eg SDNC)
  • Component/memory optimization: Ongoing Assessment

  • Global optimization (e.g. shared DB) - stretch goal=shared PostgreSQL; shared MariaDB

Need to confirm testing resource to Yang Xu and what they will be able to test

#Action-clarifications will be provided on PTL Call concerning Manageability/Footprint optimization

1) have we the resources (dev/test)

2) what are the impacts on the other requirements + backward compatibility & migration path from Casablanca Architecture to Dublin Architecture

#action to split per item

S3P - Footprint Optimization (Integration with Alpine)OOM + ALL

https://wiki.onap.org/download/attachments/45293323/Dublin-Footprint-Optimizations.pdf?version=1&modificationDate=1544543600000&api=v2

CIA Dublin Release Planning




SDC: N

CCSDK, CLAMP: Committed

Multi-VIM/loud: committed

Policy: committed

DCAE: Not committed

SDC: no resources


DCAE: Resource constraint




1

phase 1

manual

magic word "run-helm-deploy" in queue at LF, Orange and Log team

Move to POC

split per item


CI/CD

OOM + Integration

(Infrastructure)


TSC-25 - Getting issue details... STATUS

Integration

Logging

OOM

+ ALL (helm charts)

L

no except devops/scripts

in

oom/integration

OOM:

Linux Foundation (C)

Orange (C)

Bell (C)

Amdocs (C)

Logging:

Bell (C)

Amdocs (C)

Integration:



Amdocs

Orange

Linux Foundation

Bell

Huawei



1

Document as You CodeALLTracked in JIRA - Label: Documentation







1
#Action - provide findings on the PTL callSecurity by DesignSecurity SubcommitteeALL

https://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Security%20-%20Requirements-pa2.pptx?version=1&modificationDate=1544453068000&api=v2









1
#Action on TSCModeling M3 Checklist enhancementModeling SubcommitteeSO, SDC, VFC, APPC, VNFSDKProposed M3 Checklist modeling updates discussion


VFC: Committed



1

#Action - Need to be discussed on the PTL Call


Phasing approach:

#0 conf change only

#1 upgrade with no data schema change

#2 upgrade with data schema change

S3P - Provide Upgrade CapabilitiesOOM + ALLDublin Release Platform Maturity





In Dublin will establish plan & basis for platform release upgrade strategy to be implemented in following release.
1

Move Helm Chart (OOM) at project levelOOM + ALL



During the PTL meeting on 12/17 -it was agreed that

No enforcement to make it happen for all project in Dublin release, but expectation to to completed within El Alto release. This could potentially be a S3P items.

6 projects have been identified for trial: Logging, Policy, APPC, CLAMP, AAI and ONAP CLI




1

oParent Integration to fix vulnerabilities

Security Subcommittee

Yang Xu

Integration +ALL


Modeling: TO

AAI, DCAE, DMaaP, Holmes, Logging, Modeling, MSB, Multi-Cloud, ONAP CLI, UUI, Policy, Portal, SO, VFC, VNFSDK, AAF,CLAMP, MUSIC: Already Integrated

ExtApi, VID: Committed

SDC: Not Committed

CCSDK/SDNC, OOM, APPC, OOM: No

CCSDK/SDNC, APPC: dependency on ODL

OOF (HAS, OSDF): python, not Java

SDC: No resource

OOM: No java code





1

CIST running OOMPTLsNeed to assess
Infrastructure capacity






2See Dublin Release Platform Maturity#Action - Need to be discussed on the PTL CallS3P- Geo-RedundancyOOM/MUSIC Integration to ONAP ComponentsDublin Release Platform Maturity







2

Need to confirm testing resource to Yang Xu and what they will be able to test by 2/4 otherwise this item will be descoped

SOL 004 (VNF Package Security)Samuli KuuselaSDC, VNFSDK

SDC:
SDC-1980 - Getting issue details... STATUS
Jira is for PNF package.

VNFSDK:
Partially implemented in Casablanca
.

VNFSDK-342 - Getting issue details... STATUS




SDC: Partially committed (based on Ericsson contribution)



3
#action - Stephen/SECCOM to follow-up on testingxNF communication security enhancementsAAF, DCAE, ControllersSlide presented on PTL Call (1/14/2019)


DCAE - Committed based on Nokia's contribution


Controller part (SDNC) committed from Ericsson, see 5G UC





4

S3P - Service Mesh (ISTIO)Security & Architecture SubcommitteesALL except MSB or performed at K8S level (OOM); Poc of ISTIO plug-in to AAF not resourcedhttps://wiki.onap.org/download/attachments/45293323/2018-12%20Virt%20F2F%20-%20%20Dublin%20Architecture%20Requirements-pa3.pptx?version=1&modificationDate=1544650581000&api=v2







4

S3P Manageability - Logging Capabilities

see yellow/red in

in progress

log, aaf cli, consul, contrib, dcae, dmaap, nbi, oof, sdnc, so, uui, vid, vnfsdk, vvp

good

aai, appc, clamp, esr, multicloud, policy, pomba, portal, sdc, vfc


Library: In progress portal/sdk and possible so library adjustment

PORTAL-348 - Getting issue details... STATUS

Infrastructure: dmaap is adding containers, need to work with other teams in red

DMAAP-853 - Getting issue details... STATUS

as part of overall

LOG-487 - Getting issue details... STATUS

Log

OOM

Portal

SO

AAI


OOM (c)

LOG (c)

Portal (c)

SO (c)

AAI (c)

Multicloud(c)

LOG/POMBA

OOM



Amdocs

AT&T

Bell

Hauwei

Intel




3
Need to confirm testing resource to Yang Xu and what they will be able to test - to be concluded on 2/4Locale/Internationalization language supportPortal, UsecaseUIInternationalization language supportPortal, UsecaseUIL

Code:
PORTAL, UsecaseUI

UsecaseUI (C)



3

Angular 6 Upgrade of ONAP Portal and SDKPortal

PORTAL-330 - Getting issue details... STATUS

PortalXL

Code:

PORTAL

TO:

Policy, VID

PORTAL (C)



(star) T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.