DRAFT PROPOSAL FOR COMMENTS

The content of this template is expected to be fill out for M1 Release Planning Milestone.


Overview

Project NameVNFRQTS
Target Release NameBeijing
Project Lifecycle StateEither Incubation, Core, Mature. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information
Participating Company AT&T, China Mobile, Orange, Bell Canada, Amdocs, VMWare, Huawei, ZTE, Intel

Scope

What is this release trying to address?

  • This project will deliver a unified set of VNF Guidelines and Requirements.
    • The VNF Guidelines and Requirements must be  versioned to enable evolution based on operational experience
    • The VNF Guidelines and Requirements will support the ONAP Architecture Principles.
  • Identify a list of features and functionality will be developed.
    • The VNF Guidelines and Requirements will support the Release 1 Use Cases.
      • Use cases focused on VNF Requirements may be developed in this project, and they will need to be aligned with the ETE Platform use cases.  
    • It will be incorporating and integrating the source material on VNF Guidelines and Requirements from OPEN-O and ECOMP in Release 1 
    • VNF Guidelines and Requirements  are to be refined beyond prototype text  (e.g. through EPIC statements, use cases)  to deliver test cases and test procedures for us in VNF onboarding & validation. VNF Requirement level use cases to be aligned with ETE platform use cases
  • Identify what is in or out of scope. During the development phase, it helps reduce discussion.
    • VNF Guidelines may be forward looking, or include best practices in VNF design and VNF lifecycle processes.
    • VNF Requirements from ONAP APIs should be linked to the ONAP Release
    • VNF  Requirements may include: 
      • expected  operational characteristics ( e.g. security, resilience, upgradeability) 
      • conditional  requirements (e.g. When configured for deployment on High Availability Network Cloud Infrastructure, the VNF Shall …)

Use Cases

Describe the use case this release is targeted for (better if reference to customer use case).

The TSC identified the following Use cases for Release A:

TSC Use Case

VNFs identified in TSC Use case

(obselete)Use Case: VoLTE (vIMS + vEPC)N/A
Use Case: Residential Broadband vCPE (Approved)

vBNG, vG_MUX, vG,  vAAA, vDHCP, vDNS

Use Case: vFW/vDNS (Approved)

vFW, vPacketGenerator, vDataSink, vDNS, vLoadBalancer,

all VPP based.

Use Case: VoLTE(approved)

vSBC, vPCSCF, vSPGW, vPCRF, VI/SCSCF, vTAS, VHSS, vMME



The VNF Requirements developed by this project are applicable to the VNFs identified in the TSC E2E use cases.  

  • a  VNF Provider (developer) using VNF Requirements in designing, testing, and certifying a VNF for use on ONAP
  • Service Provider using VNF Requirements as prototype text for RFPs to acquire VNFs to run in an ONAP context see VNFRQTS-16
  • VNF Validation Project uses VNF Test Descriptions developed by this project to implement VNF testing for validation purposes. 

Minimum Viable Product

  • A set of Integrated VNF Requirements for use as prototype RFP text.
  • VNF Test Descriptions for use by VNF Validation project

Functionalities

List the functionalities that this release is committing to deliver by providing a link to JIRA Epics and Stories. In the JIRA Priority field, specify the priority (either High, Medium, Low). The priority will be used in case de-scoping is required. Don't assign High priority to all functionalities.

Epics

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Stories

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh


Longer term roadmap

Indicate at a high level the longer term roadmap. This is to put things into the big perspective.

Release Deliverables

Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note...) of this release.

Deliverable NameDeliverable Description
VNF Guidelines

Documentation. Provides a high level informative overview of guidance towards VNF providers.

(provided since Amsterdam release)

VNF Requirements

Documentation. Provides individually numbered requirements for VNFs

(provided since Amsterdam release)

VNF Use Cases

Documentation. Provides guidelines for VNF providers on use cases on interest to VNF providers

(new deliverable in Beijing release)

VNF Test Case

Documentation. Provides test case descriptions for how to test VNFs.

(new deliverable in Beijing release)

VNF EPICsdocumentation ( future)

Sub-Components

DeliverablerepoFiles Structure of repo
VNF Guidelines:vnfrqts/guidelinesFile per chapter
VNF Requirements:vnfrqts/requirementsFile per chapter
VNF Use Cases:vnfrqts/usecasesFile per Use Case
VNF Test Descriptions:vnfrqts/testcasesFile Per Test Case Dscription
VNF EPICs:vnfrqts/epicsnot used in Beijing Release


Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.

ONAP Dependencies

Other ONAP projects that this VNF Requirements project depends on:

Architecture

High level architecture diagram

At that stage within the Release, the team is expected to provide more Architecture details describing how the functional modules are interacting.

Block and sequence diagrams showing relation within the project as well as relation with external components are expected.

Anyone reading this section should have a good understanding of all the interacting modules.

API Incoming Dependencies

List the API this release is expecting from other releases.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
APPC   VNF configuration  requirementsM2M3APPC Documentation
Authentication and authorization Framework VNF Security RequirementsM2M3
DCAE VNF reporting requirementsM2M3DCAE APIs documentation
Modeling  Tosca Data Modeling for VNFN/A
ONAP Modelling Specifications
Multi-VIM/ MultiCloudnetwork cloud infrastructure requirementsN/A
MultiCloud Documentation
SDN-C  API requirements on VNFsM2M3SDNC APIs documentation
Service Design & Creation    VNF onboardingM2M3SDC documentation
VF-C  VNF life cycle management and configurationM2M3VF-C APIs documentation

API Outgoing Dependencies

API this release is delivering to other releases.

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
To fill outHigh level description of the APIDate for which the API is reviewed and agreedTo fill outLink toward the detailed API description

Third Party Products Dependencies

Third Party Products mean products that are mandatory to provide services for your components. Development of new functionality in third party product may or not be expected.
List the Third Party Products (OpenStack, ODL, RabbitMQ, ElasticSearch,Crystal Reports, ...).

NameDescriptionVersion
To fill outTo fill outTo fill out

In case there are specific dependencies  (Centos 7 vs Ubuntu 16. Etc.) list them as well.

Testing and Integration Plans

Provide a description of the testing activities (unit test, functional test, automation,...) that will be performed by the team within the scope of this release.

Describe the plan to integrate and test the release deliverables within the overall ONAP system.
Confirm that resources have been allocated to perform such activities.

Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

Gaps identifiedImpact
To fill outTo fill out

Known Defects and Issues

Provide a link toward the list of all known project bugs.

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Risk identifiedMitigation PlanContingency Plan
To fill outTo fill outTo fill out

Resources

Fill out the Resources Committed to the Release centralized page.

Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

Team Internal Milestone

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.

It is not expected to have a detailed project plan.

DateProjectDeliverable
1/8/18VNF RequirmentsDraft M1 Project Plan available on VNFRQTS Project Wiki
1/18/18VNF RequirmentsONAP Beijing M1 Milestone
2/12/18VNF RequirmentsONAP Beijing M2 Milestone
3/8/18VNF RequirmentsONAP Beijing M3 Milestone
3/29/18VNF RequirmentsONAP Beijing M4 Milestone
4/19/18VNF RequirmentsONAP Beijing RC0 Milestone
5/3/18VNF RequirmentsONAP Beijing RC1 Milestone
5/17/18VNF RequirmentsONAP Beijing RC2 Milestone
5/24/18VNF RequirmentsONAP Beijing Signoff Milestone

Documentation, Training

  • Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
  • Highlight the team contributions to the overall Release Documentation and training asset
  • High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
  • Documentation includes items such as:
    • Installation instructions
    • Configuration instructions
    • Developer guide
    • End User guide
    • Admin guide
    • ...

Note

The Documentation project will provide the Documentation Tool Chain to edit, configure, store and publish all Documentation asset.


Other Information

Vendor Neutral

If this project is coming from an existing proprietary codebase, ensure that all proprietary trademarks, logos, product names, etc. have been removed. All ONAP deliverables must comply with this rule and be agnostic of any proprietary symbols.

Free and Open Source Software

FOSS activities are critical to the delivery of the whole ONAP initiative. The information may not be fully available at Release Planning, however to avoid late refactoring, it is critical to accomplish this task as early as possible.
List all third party Free and Open Source Software used within the release and provide License type (BSD, MIT, Apache, GNU GPL,... ).
In the case non Apache License are found inform immediately the TSC and the Release Manager and document your reasoning on why you believe we can use a non Apache version 2 license.

Each project must edit its project table available at Project FOSS.


Charter Compliance

The project team comply with the ONAP Charter.