You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 91 Next »

M2 Functionality Freeze Status Summary

M3 API Freeze Status Summary

M4 Code Freeze Status Summary as presented at M4 review on Sept 28. Details on projects are available.

RC0 Release Candidate Summary as presented for RC0 review on Oct 12.Details on projects are available.

RC1 Release Candidate Summary as presented for RC1 review on Oct 26. Details on projects are available.


Project NameM0 Kick-Off

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

1A & AI Pass

Pass

Release Planning

Checklist

Pass on Sept 19Pass on Sept 24Pass on Oct 12Pass on Oct 12PassIn Progress
2Application Authorization FrameworkPass

Pass

Release Planning

Checklist

Pass on Oct 5Pass on Oct 5

Did not meet the Oct 2 criteria for Amsterdam

Pass on Oct 5

Did not meet the Oct 2 criteria for AmsterdamDid not meet the Oct 2 criteria for AmsterdamDid not meet the Oct 2 criteria for Amsterdam
3APPCPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 21Pass Sept 28Pass on Oct 12PassIn Progress
4CLAMPPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 11Pass Sept 28Pass on Oct 12PassIn Progress
5Common Controller SDKPass

Pass

Release Planning

Checklist

Pass on Oct 5Pass on Oct 5Pass on Oct 5Pass on Oct 12PassIn Progress
6DCAEPass

Pass

Release Planning

Checklist

Pass on Sept 12Pass Sept 28Pass Oct 2Pass on Oct 12Pass on Nov 2In Progress
7DMaaPPass

Pass

Release Planning

Checklist

Pass on Oct 10Pass on Oct 10Pass on Oct 10Pass on Oct 12PassIn Progress
8DocumentationPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 11Pass Sept 28Pass on Oct 12Pass

9External API FrameworkPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 11Pass Sept 28Pass on Oct 12Pass

10HolmesPass

Pass

Release Planning

Checklist

Pass on Sept 8Pass on Sept 8Pass Sept 28Pass on Oct 12PassIn Progress
11IntegrationPass

Pass

Release Planning

Checklist

Pass on Aug 3Pass on Aug 24Pass Sept 28Pass on Oct 12PassIn Progress
12Logging Enhancements Project Pass

Pass

Release Planning

Checklist

Pass on Sept 8Pass on Sept 8In ProgressIn ProgressPass on Nov 2

13Microservices BusPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 11Pass Sept 28Pass on Oct 12PassIn Progress
14ModelingPass

Pass

Release Planning

Checklist

In ProgressIn ProgressPass Sept 28Pass on Oct 12Pass on Nov 2In Progress
15Multi VIM/CloudPass

Pass

Release Planning

Checklist

Pass on Sept 27Pass on Sept 27Pass Sept 28Pass on Oct 12Pass

16CLIPass

Pass

Release Planning

Checklist

Pass on Aug 3

Pass on Sept 11

Pass Sept 28Pass on Oct 12PassIn Progress
17ONAP Operations ManagerPass

Pass

Release Planning

Checklist

Pass on Sept 26Pass on Sept 26Pass Sept 28Checklist filled out on Oct 28Checklist available on Oct 28In Progress
18ONAP Optimization Framework

Pass

Not planned in Amsterdam ReleaseNot planned in Amsterdam ReleaseNot planned in Amsterdam ReleaseNot planned in Amsterdam ReleaseNot planned in Amsterdam ReleaseNot planned in Amsterdam ReleaseNot planned in Amsterdam Release
19ONAP UniversityPassNo evidenceNo evidenceNo evidenceDecision to re-categorize this project under a sub-committeeDecision to re-categorize this project under a sub-committeeDecision to re-categorize this project under a sub-committeeDecision to re-categorize this project under a sub-committee
20Usecase UIPass

Pass

Release Planning

Checklist

Pass on Sept 28Pass Oct 1Pass Oct 1Pass on Oct 12Pass

21Policy FrameworkPass

Pass

Release Planning

Checklist

Pass on Sept 11Pass on Sept 11Pass Sept 28Pass on Oct 12PassIn Progress
22Portal PlatformPass

Pass

Release Planning

Checklist

Pass on Sept 12Pass on Sept 21Pass Sept 28Pass on Oct 12PassIn Progress
23SDN-CPass

Pass

Release Planning

Checklist

Pass Sept 28Pass Sept 28Pass Sept 28Pass on Oct 17PassIn Progress
24Service Design & CreationPass

Pass

Release Planning

Checklist

In ProgressIn ProgressPass on Oct 23Pass on Oct 23PassIn Progress
25Service OrchestratorPass

Pass

Release Planning

Checklist

Pass on Aug 31

Pass on Sept 11

Pass on Oct 8Pass on Oct 12PassIn Progress
26VF-C: Virtual Function ControllerPass

Pass

Release Planning

Checklist

Pass on Aug 20

Pass on Sept 14

Pass on Oct 8Pass on Oct 12PassIn Progress
27VIDPass

Pass

Release Planning

Checklist

Pass on Sept 26Pass on Oct 9Pass on Oct 9Pass on Oct 17PassIn Progress
28VNF SDKPass

Pass

Release Planning

Checklist

Pass on Aug 20Pass on Sept 6Pass Sept 28Pass on Oct 12PassIn Progress
29VNF RequirementsPass

Pass

Release Planning

Checklist

Pass on Sept 13Pass on Sept 13Pass Sept 28Pass on Oct 12PassIn Progress
30VNF Validation ProgramPass

Pass

Release Planning

Checklist

In ProgressIn ProgressDid not meet criteria for AmsterdamDid not meet criteria for AmsterdamDid not meet criteria for AmsterdamDid not meet criteria for Amsterdam
  • No labels