This page summarizes the projects participating into Casablanca Release.
M1 Status
All projects along with Functional, Non-Functional and Uses Cases marked with a green checked mark passed M1. TSC approved M1 on July 5 (Topic 3, section g)
Deck as approved on July 5 is available in wiki.
July 19 Update: Scope Change. From a Casablanca scope perspective, there are 2 additional functional requirements added:
- Change Management – Trafic Migration
- Change Management – PNF Software Upgrade
Slide deck has been updated accordingly.
M2 Status
All projects passed M2 Functionality Freeze. TSC Approval (Topic #5, Section Y )
M3 Status
M3 review took place on August 23, 2018.
Main Outcome:
AAF, ExtAPI, VVP and VNFRQTS are conditionally approved until they undergo Architecture review which is scheduled on Tuesday, August 28.
TSC approved all other projects
M3 Update: Thursday, August 30. AAF, ExtAPI, VVP and VNFRQTS have gone through the Architecture review. TSC approved M3 milestone (Topic 3, Item 2).
M4 Status
M4 review took place on Sept 20, 2018.
Materials:
TSC is currently in the process approving the Release Manager Recommendations.
Release Manager recommendation (as per slide # 35)
- Pass projects who have submitted checklist on time (specifically all project but SDC and UseCase UI)
- Get Action Items addressed within 1 week
Action Items:
- Slide #4: Michael Lando to review Bugs impacting HPA
- Slide 7-12: Vimal Begwani to provide status on 5 G implementation STATUS DONE
- Slide 12: Sarat Puthenpura to provide ETA on 5G Performance Analysis and Optimization STATUS DONE
- Slide #16: PTLs to update Casablanca Platform Maturity table at https://wiki.onap.org/display/DW/Casablanca+Release+Platform+Maturity
- Slide #16: Gildas to add Platform Maturity table in M4 checklist. STATUS DONE
- Slide #23: Catherine Lefevre to update status on OSAM/PNF (postpone to Dublin or not) STATUS: POSTPONEDOSAM postpone to Dublin. Best effort for PNF Onboarding.
- Slide #25: Impacted PTLs to fix CSIT Failure. STATUS DONE for DCAE, Multicloud, VFC, ExtAPI. FAILUREAAI, OOF, DMAAP.
- Slide #27: Jonathan Gathman and Michael lando to increase code coverage for aaf-auth and sdc master and provide update on repos for which there is no report in Sonar. STATUS: WON'T REACH 50% GOALJonathan Gathman indicated that he won't be able to reach the 50% target got AAF by lack of resource.
- Slide #28: Impacted PTLs to publish Vulnerability report. Steven Wright to follow up with Gildas for VVP. STATUS DONE for VVP, Multicloud, .
- Slide #29-30: Impacted PTLs: Clean or Fix Job Failure
- Slide #32: OOF team for ensure Healthcheck passes. STATUS DONE OOF pass on both Wind River OOM Release and Staging.
- Slide # 33 Risks: Jonathan Gathman and Manoop Talasila to address risks #3 on CADI. STATUS: Risk #3 closed. DONE