| Project Name | Project Tech. Lead | M0 Kick-Off/Intention Submission | M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery |
---|
1 | A & AI | | Dec 3, 2018 | AAI R4 M1 Release Planning AAI R4 M1 Deliverables for Planning Milestone Checklist | AAI R4 M2 Deliverables for Functionality Freeze Milestone Checklist | AAI R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration Checklist items: "Has the project passed the Integration Sanity Tests?"
|
|
|
|
|
|
2 | Application Authorization Framework | | Dec 3, 2018 | AAF R4 - M1 Release Plan AAF R4 - M1 Milestone Checklist | AAF R4 - M2 Functionality Freeze Milestone Checklist Condition: aaf-authz @55% by M3
| AAF R4 -M3 Deliverables for API Freeze Milestone Checklist Failing Sonar coverage: aaf-authz Need to update the checklist including Modeling Checklist item Gerrit: https://gerrit.onap.org/r/#/c/78520/ https://gerrit.onap.org/r/#/c/79224/ |
|
|
|
|
|
3 | APPC | | Yes, per default | APPC Dublin M1 Release Planning APPC Dublin M1 Checklist APPC Dublin M1 Security Checklist | APPC Dublin M2 Functionality Freeze Checklist | APPC Dublin M3 Deliverables for API Freeze Milestone Checklist Template
|
|
|
|
|
|
4 | CLAMP | | Yes, per default | CLAMP R4 - M1 Release Planning CLAMP R4 - M1 Deliverables for Planning Milestone Checklist | CLAMP R4 - M2 Functionality Freeze Milestone Checklist | CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist
Checklist complete - no swagger API doc |
|
|
|
|
|
5 | Common Controller SDK | | Yes, per default | CCSDK : Dublin: Release Planning CCSDK : Dublin M1 : Deliverables for Planning Milestone | CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3 | CCSDK : Dublin M3 : API Freeze Milestone Checklist Checklist partially complete Check Jenkins jobs: https://jenkins.onap.org/view/Merge-Jobs/job/ccsdk-apps-master-merge-java/ Unmet Sonar goal: https://sonar.onap.org/dashboard?id=org.onap.ccsdk.dashboard%3Accsdk-app-parent |
|
|
|
|
|
6 | DCAE | | Dec 5, 2018 | DCAE R4 M1 Release Planning DCAE R4 M1 Milestone Checklist | DCAE R4 M2 Functionality Freeze Milestone Checklist | DCAE R4 M3 Deliverables for API Freeze Milestone Checklist Waiver requested, defer coverage goal (55%) for several items until M4: dcaegen2-collectors-restconf dcaegen2-collectors-snmptrap dcaegen2-platform-inventory-api |
|
|
|
|
|
7 | DMaaP | | Yes, per default | DMaaP R4 - M1 Release Planning DMaaP R4 - M1 Milestone Checklist | DMaaP R4 - M2 Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist
Gerrit- Review https://gerrit.onap.org/r/#/c/79574/
Modeling request for data model: "waiting on modeling team." |
|
|
|
|
|
8 | Documentation | | Yes, per default | Planning worksheet M1 Documentation Dublin Release | MS2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables | Moving to weekly documentation report... no checklist |
|
|
|
|
|
9 | External API Framework | | Dec 5, 2018 | Planning worksheet M1 Checklist | | [ExtAPI] Dublin M3 API Freeze Milestone Checklist
|
|
|
|
|
|
10 | Holmes | | Dec 3, 2018 | Holmes Release Planning for Dublin Holmes Deliverables for Planning Milestone Checklist for Dublin | Holmes Deliverables for Functionality Freeze Milestone Checklist for Dublin Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28 |
|
|
|
|
|
|
11 | Integration | | Yes, per default | Integration Dublin M1 Deliverables for Planning Milestone Checklist | Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Provide status on the plan to close the blocker(s). | Integration Dublin M3 Deliverables for API Freeze Milestone Checklist Check Jenkins Jobs: https://jenkins.onap.org/view/Merge-Jobs/job/integration-master-version-manifest-merge-java/ (fixed) https://jenkins.onap.org/view/integration/job/integration-master-sniroemulator-docker-merge/ (fixed) https://jenkins.onap.org/view/integration/job/integration-master-version-manifest-merge-java/ (fixed) https://jenkins.onap.org/view/integration/job/integration-master-version-manifest-verify-java/ (fixed) |
|
|
|
|
|
12 | Logging Enhancements Project Including POMBA | | Nov 16, 2018 | Logging Dublin M1 Release Planning Logging Dublin Deliverables for Planning Milestone Checklist | Logging Dublin M2 Deliverables for Functionality Freeze Milestone Checklist | Logging Dublin M3 Deliverables for API Freeze Milestone Checklist Template Checklist complete. No swagger API data |
|
|
|
|
|
13 | Microservices Bus | | Nov 30, 2018 | MSB Release Planning for Dublin MSB Deliverables for Planning Milestone Checklist for Dublin | MSB Dubin Deliverables for Functionality Freeze Milestone Checklist-M2 | MSB Deliverables for API Freeze Milestone Checklist for Dublin No plans to address the architecture review issue: https://jira.onap.org/browse/ONAPARC-253 |
|
|
|
|
|
14 | Modeling | | Dec 3, 2018 | Modeling Dublin Planning Modeling Dublin Deliverables for Planning Milestone Checklist | Modeling Dublin Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | Modeling Dublin Deliverables for API Freeze Milestone Checklist Sonar reporting warning: modeling-toscaparsers-javatoscachecker |
|
|
|
|
|
15 | Multi VIM/Cloud | | Dec 3, 2018 | MultiCloud Dublin Release Planning Deliverables for Planning Milestone Checklist | Deliverables for Functionality Freeze Milestone Checklist - Conditions: Get all remaining unit test code coverage > 55% by M3
- Plan to design container(s) as non-root: M3 Dublin
| MultiCloud R4 Deliverables for API Freeze Milestone Checklist Conditional: Need to add Modeling checklist item Review gerrit (stale merges) https://gerrit.onap.org/r/#/c/76324/ https://gerrit.onap.org/r/#/c/75851/ |
|
|
|
|
|
16 | MUSIC | | Yes, per default | MUSIC Dublin Release Planning MUSIC Dublin M1 Deliverables for Planning Milestone Checklist | MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: unit test coverage > 55% by M3. | MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist
|
|
|
|
|
|
17 | ONAP CLI | | Dec 3, 2018 | Dublin-M1-CLI Deliverable Dublin-M1-CLI Release planning | Dublin-M2-Checklist | Dublin-M3 checklist Need to update the checklist including Modeling Checklist item |
|
|
|
|
|
18 | ONAP Operations Manager | | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist
| OOM Dublin - M3 API Freeze Milestone Checklist -Review gerrit: https://gerrit.onap.org/r/#/c/72189/ https://gerrit.onap.org/r/#/c/80030/ https://gerrit.onap.org/r/#/c/78353/ https://gerrit.onap.org/r/#/c/79268/ https://gerrit.onap.org/r/#/c/79990/ https://gerrit.onap.org/r/#/c/79347/ https://gerrit.onap.org/r/#/c/79989/ https://gerrit.onap.org/r/#/c/79330/ https://gerrit.onap.org/r/#/c/79985/ https://gerrit.onap.org/r/#/c/78873/ https://gerrit.onap.org/r/#/c/77439/ |
|
|
|
|
|
19 | ONAP Optimization Framework | | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 |
|
|
|
|
|
20 | ONAP Usecase UI | | Yes, per default | Usecase-UI Beijing Release Planning Dublin Release M1 Deliverables for Planning Milestone Checklist | UUI Dublin M2 Functionality Freeze Milestone Checklist | Dublin Release M3 Deliverables for API Freeze Milestone Checklist
Please complete more of the checklist |
|
|
|
|
|
21 | Policy Framework | | Dec 3, 2018 | Policy R4 Dublin M1 Release Planning Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template | Policy R4 Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template | Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template
|
|
|
|
|
|
22 | Portal Platform | | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | Portal R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration & Modeling Checklist items Gerrit: Review https://gerrit.onap.org/r/#/c/78714/ (this is addressed now, no pending reviews as of March 12) Fix Integration Blocker
PORTAL-530
-
Getting issue details...
STATUS
|
|
|
|
|
|
23 | SDN-C | | Yes, per default | SDNC : Dublin: Release Planning SDNC : Dublin M1 : Deliverables for Planning Milestone | SDNC : Dublin M2 : Functionality Freeze Milestone Checklist Condition: Unit test code coverage > 55% by M3 | https://wiki.onap.org/display/DW/SDNC+%3A+Dublin+M3%3A+Deliverables+for+API+Freeze+Milestone+Checklist Missing swagger API info Not yet met: Unit test code coverage > 55% by M3 Supporting links not provided in checklist
|
|
|
|
|
|
24 | Service Design & Creation | | Dec 4, 2018 | SDC R4 Release Planning SDC R4 Deliverables for Planning Milestone Checklist | SDC R4 Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | |
|
|
|
|
|
25 | Service Orchestrator | | Dec 2, 2018 | SO Dublin M1 Release Planning SO Dublin M1 Checklist | Service Orchsttrator M2 Checklist |
SO-1617
-
Getting issue details...
STATUS
|
|
|
|
|
|
26 | VF-C: Virtual Function Controller | | Dec 2, 2018 | VF-C Dublin M1 Release Planning VF-C Dublin: Deliverables for Planning Milestone Checklist | VF-C Dublin: Deliverables for Functionality Freeze Milestone Checklist Template | |
|
|
|
|
|
27 | VID project | | Dec 4, 2018 | VID R4 M1 Release Planning VID R4 M1 Deliverables for Planning Milestone Checklist | VID R4 M2 Deliverables for Functionality Freeze Milestone Checklist | VID R4 M3 Deliverables for API Freeze Milestone Checklist Changes since M1? Missing swagger API info Fix Integration Blocker:
VID-429
-
Getting issue details...
STATUS
|
|
|
|
|
|
28 | VNF SDK | | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 | VNF SDK Dublin API Freeze(M3)
|
|
|
|
|
|
29 | VNF Requirements | | Nov 16, 2018 | Dublin Release Plan for VNFRQTS M1 Deliverables for Planning Milestone Checklist Template | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist |
|
|
|
|
|
30 | VNF Validation (VVP) | | Nov 16, 2018 | Dublin Release Plan for VVP M1 Deliverables for Planning Milestone Checklist Template | M2 Deliverables for Functionality Freeze Milestone Checklist Template
| M3 Deliverables for API Freeze Milestone Checklist Template |
|
|
|
|
|