This page summarizes the projects that are within the scope of Beijing Release.
At M1 Release Planning milestone, Jan 18, 2018, the TSC will review all project planning materials and provide its disposition. It is expected that all projects intending to participate into Beijing submit their Project Planning Materials no later than Jan 8, 2018.
That will provide time for everyone to:
- understand each project scope
- review dependencies
- review all M1 materials
- ask openly question
- smooth the TSC approval process
Calendar for Beijing Release.
For those who intend to propose a new project, use the ONAP Project Proposal Template and post it in the Proposed Project list.
New project proposal for Beijing are available here. These new projects will be reviewed by TSC during Santa Clara F2F the week of Dec 11-13 amd added to the list below as they are approved byTSC.
M1 Status
Conditions on projects:
- AAF: Pass with condition TSC need to agree on expending to CSM sub project scope.
- AAI: Pass with condition TSC need to agree on expending to Image Manager sub project scope. Gildas Lanilis Update Feb 8. Team's decision to defer Image Manager to Casablanca.
- DCAE: Pass with condition on exception Cloudify manager.
- LOG: Pass with condition to review security guidelines and badges.
- OOM: Pass with Condition to Clarify Maturity scope.
- SO: Pass with Condition to reach 2 for Resiliency and Scalability at cpts Level (strectch ). Should be OK for 2 at Platform level.
Action Items:
- Benchmark-Integration (Jason-Helen) team to provide performance measurement by M2.Update by Gildas Lanilis: Information provided during Virtual F2F: Integration Testing and S3P Measurement (slide #17). Action Items: Closed
- Action Item: Auto-scaling: need for Blandford Scott and Zhao Peng to bring clarification on requirements. Update by Gildas Lanilis : Peng Zhao made clarification with VFC PTL, Scott Blandford broght clarification on the scope of Auto-scaling for Beijing. Action Items: Closed
M1 Summary of findings
Link to M1 IRC notes.
M2 Status
TSC did not reach quorum today, therefore no vote took place. M2 Recommendations are provided and send out by email for vote.
Recommendations to TSC:
Disposition M2 as Pass for aaf,aai, appc, ccsdk, clamp, cli, dcagen2, dmaap, doc, externalapi, holmes, integration, logging, modeling, msb, music, oof, oom, policy, portal, sdnc, so, vfc, vid, vnfrqts, vnfsdk. Update by Gildas Lanilis: TSC approved the disposition by mailing list vote.
- 3 projects (sdc, usecase UI, multicloud) could not make it today and are schedule for review at next TSC meeting. Update by Gildas Lanilis: TSC approved these 3 project during TSC meeting on Feb 22.
- TSC needs to discuss on VVP. Current status: VVP did not presnt to M1 and M2 and there are some thoughts on breaking thins into a sub-committe and a project.
Action Items:
- Auto-Scaling: carried over from M1. Peng Zhao and VFC team to clarify.See M1 note above. Action Items: Closed
- SO external API: Eric Debeau to contact Seshu Kumar Mudiganti for questions and concerns. Action Items: Closed
Link to M2 IRC notes.
M3 Status
All projects except VVP and logging passed M3 milestone.
Action Items:
- Logging: checklist was not available. Review will be hold during next week TSC meeting. Action Items: Closed (datails here, slide #3)
- VVP: Steven Wright to organize meeting to review and clarify S3P scope for VVP. (Invitees: Brian Freeman, Helen Chen, Gildas Lanilis) Action Items: Closed (datails here, slide #4)
Link to M3 IRC notes.
M4 Status
All projects passed except: Usecase-ui, ExternalAPI, AAF, DMAAP. TSC was running out of time to provide its disposition on VVP.
Action Items:
- PTL: Look for details in colunm "M4 notes and Disposition" in PDF file, plus all the items highlighted in Red.
- PTL: ensure the Functional Requirement and Platform Maturity table are up to date
- PTL: update project risk
Beijing Vulnerability Reports
This list projects who have fill out a vulnerability report for Beijing Release.
Beijing Milestones Status
| Project Name | Project Tech. Lead | M0 Kick-Off/Intention Submission
| M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery |
---|
1 | A & AI | | Oct 25, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist | Checklist |
|
|
|
2 | Application Authorization Framework | | Nov 5, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist | Checklist |
|
|
|
3 | APPC | | Nov 4, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
4 | CLAMP | | Oct 30, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
5 | Common Controller SDK | | Oct 13, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
6 | DCAE | | Nov 4, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist | Checklist |
|
|
|
7 | DMaaP | | Nov 5, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
8 | Documentation | | Nov 4, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
9 | External API Framework | | Nov 7, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
10 | Holmes | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
11 | Integration | | Oct 25, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
12 | Logging Enhancements Project | | Oct 30, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist |
|
|
|
|
13 | Microservices Bus | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
14 | Modeling | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
15 | Multi VIM/Cloud | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
16 | MUSIC | | Jan 4, 2018 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
17 | ONAP CLI | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
18 | ONAP Operations Manager | | Oct 26, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist |
|
|
|
|
19 | ONAP Optimization Framework | | Nov 6, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
20 | ONAP Usecase UI Project Proposal | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
21 | Policy Framework Project Proposal | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
22 | Portal Platform Project Proposal | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
23 | SDN-C | | Oct 13, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
24 | Service Design & Creation | | Oct 28, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist |
|
|
|
|
25 | Service Orchestrator | | Oct 25, 2017 | Planning Checklist Pass with condition | Checklist | Checklist | Checklist |
|
|
|
|
26 | VF-C: Virtual Function Controller | | Oct 26, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
27 | VID project | | Oct 29, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
28 | VNF SDK | | Nov 20, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
29 | VNF Requirements | | Nov 6, 2017 | Planning Checklist Pass | Checklist | Checklist | Checklist | Checklist |
|
|
|
30 | VNF Validation (VVP) | | Oct 31, 2017 | Not reviewed by TSC. Checklist created on March 1 | Checklist created on March 1 | Checklist | Checklist | Checklist |
|
|
|