This page summarizes the projects that are within the scope of Beijing Release.
At M1 Release Planning milestone, Jan 18, 2018, the TSC will review all project planning materials and provide its disposition. It is expected that all projects intending to participate into Beijing submit their Project Planning Materials no later than Jan 8, 2018.
That will provide time for everyone to:
- understand each project scope
- review dependencies
- review all M1 materials
- ask openly question
- smooth the TSC approval process
Calendar for Beijing Release.
For those who intend to propose a new project, use the ONAP Project Proposal Template and post it in the Proposed Project list.
New project proposal for Beijing are available here. These new projects will be reviewed by TSC during Santa Clara F2F the week of Dec 11-13 amd added to the list below as they are approved byTSC.
M1 Status
Conditions on projects:
- AAF: Pass with condition TSC need to agree on expending to CSM sub project scope.
- AAI: Pass with condition TSC need to agree on expending to Image Manager sub project scope. Gildas Lanilis Update Feb 8. Team's decision to defer Image Manager to Casablanca.
- DCAE: Pass with condition on exception Cloudify manager.
- LOG: Pass with condition to review security guidelines and badges.
- OOM: Pass with Condition to Clarify Maturity scope.
- SO: Pass with Condition to reach 2 for Resiliency and Scalability at cpts Level (strectch ). Should be OK for 2 at Platform level.
Action Items:
- Benchmark-Integration (Jason-Helen) team to provide performance measurement by M2.
- Action Item: Auto-scaling: need for Blandford Scott and Zhao Peng to bring clarification on requirements.
M1 Summary of findings
Link to M1 IRC notes.
Beijing Milestones Status
| Project Name | Project Tech. Lead | M0 Kick-Off/Intention Submission
| M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery |
---|
1 | A & AI | | Oct 25, 2017 | Planning Checklist Pass with condition | Checklist |
|
|
|
|
|
|
2 | Application Authorization Framework | | Nov 5, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
3 | APPC | | Nov 4, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
4 | CLAMP | | Oct 30, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
5 | Common Controller SDK | | Oct 13, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
6 | DCAE | | Nov 4, 2017 | Planning Checklist Pass with condition | Checklist |
|
|
|
|
|
|
7 | DMaaP | | Nov 5, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
8 | Documentation | | Nov 4, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
9 | External API Framework | | Nov 7, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
10 | Holmes | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
11 | Integration | | Oct 25, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
12 | Logging Enhancements Project | | Oct 30, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
13 | Microservices Bus | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
14 | Modeling | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
15 | Multi VIM/Cloud | | Oct 26, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
16 | MUSIC | | Jan 4, 2018 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
17 | ONAP CLI | | Oct 26, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
18 | ONAP Operations Manager | | Oct 26, 2017 | Planning Checklist Pass with condition | Checklist |
|
|
|
|
|
|
19 | ONAP Optimization Framework | | Nov 6, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
20 | ONAP Usecase UI Project Proposal | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
21 | Policy Framework Project Proposal | | Oct 26, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
22 | Portal Platform Project Proposal | | Oct 26, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
23 | SDN-C | | Oct 13, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
24 | Service Design & Creation | | Oct 28, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
25 | Service Orchestrator | | Oct 25, 2017 | Planning Checklist Pass with condition | Checklist |
|
|
|
|
|
|
26 | VF-C: Virtual Function Controller | | Oct 26, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
27 | VID project | | Oct 29, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
28 | VNF SDK | | Nov 20, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
29 | VNF Requirements | | Nov 6, 2017 | Planning Checklist Pass | Checklist |
|
|
|
|
|
|
30 | VNF Validation (VVP) | | Oct 31, 2017 | Not reviewed. To be discussed at next TSC meeting |
|
|
|
|
|
|
|